Overview
THE PALATIAL PHASE 1 (TOWER-E)
HERO REALTY PRIVATE LIMITED · Gurugram
Units170
Completion2029-12-31Proposed
Registered on2025-01-31
Valid to2030-06-30
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 3 source links |
Registration
Registration
| Promoter | HERO REALTY PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/907/639/2025/10 DATED 31.01.2025 | |
| Registered on | 2025-01-31 | |
| Valid to | 2030-06-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2029-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No. 199 of 2023 dated 05.10.2023 and 15 of 2024 dated 30.01.2024 | Town & Country Planning Department | |
| Layout Plan | 2024-11-28 | ||
| Building Plan | 2024-11-28 | ||
| I. LICENSE | 2023-10-05 | ||
| II. ZONING PLAN | 2024-01-31 | ||
| III. PHASING PLAN | 2024-10-21 | ||
| IV. SITE PLAN & BUILDING PLAN | 2024-11-28 | ||
| V. AIRPORT HEIGHT CLEARANCE | 2023-11-01 | ||
| VI. FOREST NOC | 2023-08-01 | ||
| VII. FIRE FIGHTING SCHEME | 2024-12-02 | ||
| VIII. SERVICE PLAN ESTIMATE | 2024-12-03 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,68,38,96,000 | |
|---|---|---|
| Construction | ₹2,45,27,98,000 | |
| Total | ₹6,31,55,41,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 3.62 | |
|---|---|---|
| Units | 170 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 134.35 | 164 |
| Apartment/Shops/Other Buildings | 118.14 | 6 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-01-01 | |
|---|---|---|
| Proposed completion | 2029-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HERO REALTY PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/3185
- https://nominatim.openstreetmap.org/search?q=sector+104%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2025-01-31
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2024-12-07
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2024-12-07 · Sign in to download
- DEMARCATION PLAN · 2024-12-07
- ZONING PLAN · 2024-12-07
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2024-12-07
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2024-12-07
- FLOOR PLANS · 2024-12-07
- ELEVATION PLAN · 2024-12-07
- SECTION PLAN · 2024-12-07
- PARKING PLAN · 2024-12-07
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2024-12-07 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2024-12-07
- PHASING PLAN AND LETTER · 2024-12-07
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2024-12-11 · Sign in to download
- CA CERTIFICATE ESTIMATED COST · 2024-12-11 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2024-12-11 · Sign in to download
- CA CERTIFICATE COST INCURRED · 2024-12-11 · Sign in to download