THE PARKSYDE PHASE - II

RISHABH BUILDTECH INDIA PRIVATE LIMITED · RAIPUR
Units182
Booked138 of 182As of 2026-06-30
Construction progress96%As of 2026-06-30
Completion2027-01-26Revised · Proposed 2022-09-30
Registered on2018-09-29
Approvals2
Cases1

Sections

Property title & search report
Approvals2 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 32 quarters
Technical report
Site & area3 site details · 182 unit types
Construction & progress4 progress details · 32 quarters
Developer & finance
Developer3 developer details
The evidence
Sources202 documents · 9 source links

Registration

Registration

PromoterRISHABH BUILDTECH INDIA PRIVATE LIMITED
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA290918000789
Registered on2018-09-29
Project typeGroup Housing
Status (as filed)New
Proposed completion2022-09-30
Revised completion2027-01-26