DOSLChhattisgarh Workspace

Overview

THE PARKSYDE PHASE - III

RISHABH BUILDTECH INDIA PRIVATE LIMITED · RAIPUR
Units1
Booked0 of 1As of 2023-03-31
Construction progress23%As of 2023-03-31
Completion2024-06-30Revised · Proposed 2023-09-30
Registered on2018-09-29
Approvals2

Sections

Property title & search report
Approvals2 approvals
Contract & costs2 cost heads · 19 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 19 quarters
Developer & finance
Developer3 developer details
The evidence
Sources93 documents · 5 source links

Registration

Registration

PromoterRISHABH BUILDTECH INDIA PRIVATE LIMITED
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA290918000790
Registered on2018-09-29
Project typeGroup Housing
Status (as filed)New
Proposed completion2023-09-30
Revised completion2024-06-30