Photo: The Pearl ParadiseTitle & ownership
Approvals
| Building plan (BDA) | Sanctioned 28 Mar 2025 · No. BDA/EM/EO-2/TA-3/North/27/2024-25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department |
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BDA) | Sanctioned 28 Mar 2025 | |
| Escrow bank | Karur Vysya Bank Ltd. · K R Puram |
Data room
89 documents filed with K-RERA for this project
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. 1 of 2 filed survey numbers matched, 1 could not be read. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
Good project with all basic amenities and less density too. Construction team also supportive. Work is running fast as per there assurance. It's a good to go project.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Locked |
| Location & risks | – | 1 | 1 | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 1 | Clear |
| Loan & collateral | – | – | – | – |
Part of the full report. Unlock all 5 sections
| 3 Little BirdsRegistered · no quarterly update yet | Zenso Little Birds Projects LLP | Apartment | 724 sqft carpet (as filed) | Sep 2026 |
| Adarsh Palm Acres - Phase 1-Part ALapsed · completion date passed | Adarsh Nivaas Private Limited | Apartment | 1,604 sqft carpet (as filed) | Nov 2023 |
| Adarsh Palm Acres - Phase 1-Part AFiled as completed · no completion certificate on record | Bangalore Best Realty Private Limited | Apartment | – | Nov 2023 |
| Adarsh Palm Acres - Phase 1-Part BLapsed · completion date passed | Adarsh Nivaas Private Limited | Apartment | 2,906 sqft carpet (as filed) | Nov 2023 |
| Adarsh Palm Acres - Phase 1-Part BLapsed · completion date passed | Bangalore Best Realty Private Limited | Apartment | 2,906 sqft carpet (as filed) | Nov 2023 |
| Adarsh Palm Acres - Phase 2-Part ALapsed · completion date passed | Adarsh Nivaas Private Limited | Apartment | – | Nov 2023 |
| Adarsh Palm Acres - Phase 2-Part BLapsed · completion date passed | Adarsh Nivaas Private Limited | Apartment | 3,111 sqft carpet (as filed) | Nov 2023 |
| Adarsh Palm Acres (Phase III)Active · 3% built | Adarsh Developers | Villa | 3,150–5,687 sqft | 2028 |
8 of 73 other projects in Bagalur, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open The Pearl Paradise in the interactive atlas
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| Pollution board (CFE) | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2026 |
| Land conversion | Converted 6 Oct 2020 · DC Bangalore urban | |
|---|---|---|
| Survey numbers | New No.122/1 Old No.122/3 |
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main), at the filed pin | Clear |
|---|---|---|
| Nearest government-flagged flood location | 3.3 km, Telecom layout, Ashwathnagar | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | 590 m to the south-east, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 410 m to the north-west, an unnamed pond |
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Gym · Power Backup | |
|---|---|---|
| Electricity, built | 90% | |
| Community Hall, built | 90% | |
| Gym, built | 90% | |
| Covered parking per unit | 1.19 (38 covered spaces for 32 units) | |
| Power backup | Declared by the promoter |
As the promoter reported itPossession date in the agreement
| Main structure | 100% · planned by 28 Feb 2026 | |
|---|---|---|
| Electrical and plumbing finishing | 90% · planned by 30 Oct 2026 | |
| Completion | 90% |
| Possession, agreement | 31 Dec 2026 | |
|---|---|---|
| Schedule end | 30 Oct 2026 | |
| RERA completion date | 31 Dec 2026 | |
| Work began, as filed | 9 May 2025 |
| Structure | RCC framed structure | |
|---|---|---|
| Building heights, fire NOC | 15 m filed |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | UPVC windows | |
|---|---|---|
| Power backup | Provided, 9 sq m |
| Structural engineer, quarterly | Form 6 · Feb 2026, Jul 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Architect, quarterly | Form 5 · Feb 2026, Jul 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Site inspected 5 Jul 2025 | |
| Chartered accountant, Form 4 | Dated 12 Oct 2026 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹16.52 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹16.52 Cr, same as the filing | |
| Cost left | ₹4.25 Cr | |
| Receivable, sold flats | ₹4.70 Cr |
Sold (23) 71.9%Unsold (9) 28.1%
| Sold, Q3 2025-26 | 3 / 32 · 29 available | |
|---|---|---|
| Sold, Q4 2025-26 | 5 / 32 · 27 available | |
| Sold, Q1 2026-27 | 13 / 32 · 19 available | |
| Sold, Q2 2026-27 | 23 / 32 · 9 available | |
| Unsold, Q2 2026-27 | 9 | |
| Sold in Q4 2025-26 | 2 | |
| Sold in Q1 2026-27 | 8 | |
| Sold in Q2 2026-27 | 10 |
| Escrow bank | Karur Vysya Bank Ltd. · K R Puram | |
|---|---|---|
| Designated account, collected | ₹4.46 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹3.70 Cr in Q2 2026-27 (83% of that quarter's deposits) | |
| Net amount withdrawable, Form 4 | ₹5,75,23,765 | |
| Escrow account, Q4 2025-26 | Opened at ₹2.6 L, ₹1.05 Cr withdrawn | |
| Escrow account to date, Q2 2026-27 | ₹8.95 Cr deposited from sales, ₹6.5 L other deposits, ₹8.58 Cr withdrawn | |
| Escrow account to date, Q4 2025-26 | Balance ₹49.7 L | |
| Share of collections deposited in escrow | 83% | |
| Sale proceeds realised, Q3 2025-26 | ₹74,72,780 |
| K-RERA registrations under this promoter | 6 | |
|---|---|---|
| Marked completed | 0 | |
| Past promised date, not completed | 2 | |
| Other phases under this promoter name | 263 | |
| With a filed extension or completion | 120 (86 completed, 34 extended) | |
| Average schedule slip | 10 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 30.5 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru East taluk average, July 2023: 27.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes | |
| Through the year | Not found | |
| Water supply, as filed | Borewell | |
| Nearest city water main | 1.4 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 590 m to the south-east, tertiary drain | |
|---|---|---|
| Ground level | 902 m above sea level, plus or minus 4 m | |
| Metro, operational | 8.0 km, K.R. Puram | |
| Metro, under construction | 5.1 km, Nagawara |
| Kempegowda Airport | 23.8 | 26 | 15.1 |
| MG Road (CBD) | 14.6 | 19 | 12.4 |
| Manyata Tech Park | 8.7 | 13 | 5.3 |
| ITPL, Whitefield | 19.5 | 24 | 12.5 |
| Ecospace, Bellandur ORR | 25.8 | 36 | 16.3 |
| Electronic City Ph 1 | 34.8 | 43 | 25.8 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 2.9 km to the south, named Horamavu Agara 20MLD Sewage Treatment Plant on OpenStreetMap | |
| Quarry | 630 m to the north-west | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 810 m to the south |