Overview
THE SILICON COURTYARD
HI-TECH BUILDERS & PROMOTERS · Sahibzada Ajit Singh Nagar (Mohali)
Units258
Completion2029-05-06Proposed
Valid to2029-05-06
Approvals14
Sections
| Property title & search report | |
|---|---|
| Approvals | 14 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 11 unit types |
| Construction & progress | 2 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 34 documents · 25 source links |
Registration
Registration
| Promoter | HI-TECH BUILDERS & PROMOTERS | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0274 | |
| Valid to | 2029-05-06 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-05-06 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2024-02-05 | |
| CLU Certificate | ||
| Electric Substation NOC | 2025-04-16 | |
| Environment Clearance certificate/ NOC | Revisions (Received) | 2024-04-19 |
| Environment Clearance certificate/ NOC | 2023-10-06 | |
| License as Promoter from competent Authority | 2023-10-19 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-01-22 | |
| NOC from Mining Department | 2024-02-07 | |
| NOC from NHAI/ PWD | 2025-03-28 | |
| NOC from NHAI/ PWD | 2023-10-30 | |
| Other Document (AFFIDAVIT REGARDING NOCs) | Legal Documents (Received) | 2024-05-28 |
| Pollution Clearance from Punjab Pollution Control Board | 2024-03-26 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-04-09 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹12,83,15,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 18,161.022 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 10 | |
| Units | 258 |
Unit types
| GROUND FLOOR | 3,696.06 | 26 | COMMERCIAL COMPLEX WITH HOTEL |
| FIRST FLOOR | 4,895.95 | 60 | COMMERCIAL COMPLEX WITH HOTEL |
| SECOND FLOOR | 4,939.53 | 43 | COMMERCIAL COMPLEX WITH HOTEL |
| THIRD FLOOR | 2,407.19 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| FOURTH FLOOR | 460.85 | 3 | COMMERCIAL COMPLEX WITH HOTEL |
| FIFTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| SIXTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| SEVENTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| EIGHTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| NINTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
| TENTH FLOOR | 519.56 | 18 | COMMERCIAL COMPLEX WITH HOTEL |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-05-07 | |
|---|---|---|
| Proposed completion | 2029-05-06 |
Quarterly progress
| 2024-Q4 | 2025-01-31 |
| 2025-Q1 | 2025-04-30 |
| 2025-Q2 | 2025-08-01 |
| 2025-Q3 | 2025-10-31 |
| 2025-Q4 | 2026-02-11 |
| 2026-Q1 | 2026-04-16 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HI-TECH BUILDERS & PROMOTERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | BHOO CONSULTANTS |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12015&inPromoter_ID=2900&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-02-05
- Building Permit Issue from Municipal Authority · 2024-02-14 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-04-16
- Environment Clearance certificate/ NOC · 2024-04-19
- Environment Clearance certificate/ NOC · 2023-10-06
- License as Promoter from competent Authority · 2023-10-19
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-01-22
- NOC from Mining Department · 2024-02-07
- NOC from NHAI/ PWD · 2025-03-28
- NOC from NHAI/ PWD · 2023-10-30
- Other Document (AUTHORITY LETTER) · 2024-05-20 · Sign in to download
- Other Document (forest) · 2024-03-13 · Sign in to download
- Other Document (solid waste) · 2024-02-14 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2024-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-09
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-02-05
- CLU Certificate
- Electric Substation NOC · 2025-04-16
- Environment Clearance certificate/ NOC · 2024-04-19
- Environment Clearance certificate/ NOC · 2023-10-06
- License as Promoter from competent Authority · 2023-10-19
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-01-22
- NOC from Mining Department · 2024-02-07
- NOC from NHAI/ PWD · 2025-03-28
- NOC from NHAI/ PWD · 2023-10-30
- Other Document (AFFIDAVIT REGARDING NOCs) · 2024-05-28
- Pollution Clearance from Punjab Pollution Control Board · 2024-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-09
- 2024-Q4 · 2025-01-31
- 2025-Q1 · 2025-04-30
- 2025-Q2 · 2025-08-01
- 2025-Q3 · 2025-10-31
- 2025-Q4 · 2026-02-11
- 2026-Q1 · 2026-04-16
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-11