Overview
THE SKY VIEW CO-OPERATIVE GROUP HOUSING SOCIETY LTD
THE SKY VIEW CO-OPERATIVE GROUP HOUSING SOCIETY LTD PLOT NO -GH-4 SECTOR-13-17 HUDA PANIPAT · Panipat
Completion2023-10-01Revised · Proposed 2020-10-01
Valid to2023-12-31
Approvals4
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 8 documents · 3 source links |
Registration
Registration
| Promoter | THE SKY VIEW CO-OPERATIVE GROUP HOUSING SOCIETY LTD PLOT NO -GH-4 SECTOR-13-17 HUDA PANIPAT | |
|---|---|---|
| District | Panipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-PNP-144-2019 | |
| Valid to | 2023-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2020-10-01 | |
| Revised completion | 2023-10-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | Town & Country Planning Department |
| Layout Plan | |
| Building Plan | |
| I. TOWN AND COUNTRY PLANING -HUDA |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1975-2022 | HRERA Panchkula | Pending |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,28,20,00,00,000 | |
|---|---|---|
| Construction | ₹87,11,80,00,00,000 | |
| Total | ₹93,40,00,00,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,086.66 | |
|---|---|---|
| FAR | 1.75 |
Unit types
| Type |
|---|
| 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-12-18 | |
|---|---|---|
| Proposed completion | 2020-10-01 | |
| Revised completion | 2023-10-01 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | THE SKY VIEW CO-OPERATIVE GROUP HOUSING SOCIETY LTD PLOT NO -GH-4 SECTOR-13-17 HUDA PANIPAT | |
|---|---|---|
| Escrow bank | HDFC BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLVBOUC0xNDQtMjAxOQ==
- https://haryanarera.gov.in/view_project/project_preview_open/522
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-04-10
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-04-10 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-04-10
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-05-01
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-05-01
- Occupation Certificate uploaded. · 2025-05-19 · Sign in to download
- Extension Uploaded · 2026-04-01 · Sign in to download