Overview
THE SUN SHINE CITY
SAMEER INFRA PROJECTS PVT LTD · Patna
Units11
Booked0 of 11As of 2026-03-31
Construction progress35%As of 2026-03-31
Completion2022-12-31Proposed
Registered on2019-02-07
Valid to2022-12-31
Approvals6
Cases4
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 4 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 11 unit types |
| Construction & progress | 4 progress details · 27 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 55 documents · 38 source links |
Registration
Registration
| Promoter | SAMEER INFRA PROJECTS PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00304-1/232/R-405/2019 | |
| Registered on | 2019-02-07 | |
| Valid to | 2022-12-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) | ||
| Environment Clearance | 2022-12-31 | |
| Fire NOC | 2022-12-31 | DIRECTOR-CUM-STATE FIRE OFFICER |
| Airport NOC | 2022-12-31 | |
| Water Supply Permission | 2022-12-31 | |
| Other approval | 2022-12-31 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA/C-CASE-556/2022 | RERA Bihar | ||
| RERA/CC/120/2022 | RERA Bihar | Complaint | Pending |
| RERA/CC/121/2022 | RERA Bihar | Complaint | |
| RERA/CC/556/2022 | RERA Bihar | Complaint |
Complaints & cases
| Cases | 4 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,16,25,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,662.92 | |
|---|---|---|
| Built-up (m²) | 19,952.94 | |
| FAR | 3 | |
| Towers | 5 | |
| Units | 11 | |
| Booked | 0 | |
| Booked as of | 2026-03-31 |
Unit types
| 3 BHK | 1 | THE SUN CITY |
| 2 BHK | 1 | THE SUN SHINE CITY |
| 3 BHK | 1 | THE SUN SHINE CITY |
| 3 BHK | 1 | THE SUN SHINE CITY |
| 3 BHK | 1 | THE SUN SHINE CITY |
| 2 BHK | 1 | THE SUN SHINE CITY |
| 1 BHK | 1 | THE SUN SHINE CITY |
| 1 BHK | 1 | THE SUN SHINE CITY |
| 1 BHK | 1 | THE SUN SHINE CITY |
| 2 BHK | 1 | THE SUN SHINE CITY |
| 2 BHK | 1 | THE SUN SHINE CITY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 35% | |
|---|---|---|
| As of | 2026-03-31 | |
| Start | 2017-03-31 | |
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2026-Q1 | 2026-04-24 | 35% | 0 |
| 2025-Q4 | 2026-01-22 | ||
| 2025-Q3 | 2025-10-21 | ||
| 2025-Q2 | 2025-07-21 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-13 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-08-02 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 | ||
| 2022-Q4 | 2024-07-25 | ||
| 2022-Q3 | 2024-07-25 | ||
| 2022-Q2 | 2022-09-13 | ||
| 2022-Q1 | 2022-08-11 | ||
| 2021-Q4 | 2022-02-24 | ||
| 2021-Q3 | 2021-11-19 | ||
| 2021-Q2 | 2021-09-12 | ||
| 2021-Q1 | 2022-07-22 | ||
| 2020-Q4 | 2022-07-22 | ||
| 2020-Q2 | 2022-07-22 | ||
| 2020-Q1 | 2022-07-22 | ||
| 2019-Q4 | 2022-07-22 | ||
| 2019-Q3 | 2022-07-22 | ||
| 2019-Q2 | 2022-07-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAMEER INFRA PROJECTS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP274201800304-1
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP274201800304&ld=pan&pj=RERAP274201800304-1&f=2025-2026&q=4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP274201800304-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-24
- Quarterly Progress Image · 2025-07-21
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-22
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-21
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-21
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-13
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-08-02
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2024-07-25
- Q2-Jul to Sep / 2022-2023 · 2024-07-25
- Q1-Apr to Jun / 2022-2023 · 2022-09-13
- Q4-Jan to Mar / 2021-2022 · 2022-08-11
- Q3-Oct to Dec / 2021-2022 · 2022-02-24
- Q2-Jul to Sep / 2021-2022 · 2021-11-19
- Q1-Apr to Jun / 2021-2022 · 2021-09-12
- Q4-Jan to Mar / 2020-2021 · 2022-07-22
- Q3-Oct to Dec / 2020-2021 · 2022-07-22
- Q1-Apr to Jun / 2020-2021 · 2022-07-22
- Q4-Jan to Mar / 2019-2020 · 2022-07-22
- Q3-Oct to Dec / 2019-2020 · 2022-07-22
- Q2-Jul to Sep / 2019-2020 · 2022-07-22
- Q1-Apr to Jun / 2019-2020 · 2022-07-22
- View · Sign in to download
- View · 2022-09-14 · Sign in to download
- View · 2022-09-14 · Sign in to download
- View · 2023-07-31 · Sign in to download
- View · 2023-10-06 · Sign in to download
- View · 2023-11-06 · Sign in to download
- View · 2024-01-18 · Sign in to download
- View · 2026-02-05 · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Other · 2024-09-02 · Sign in to download
- Other · 2022-09-14 · Sign in to download
- Other · 2022-09-14 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- RERA/C-CASE-556/2022 · Sign in to download
- RERA/CC/120/2022 · Sign in to download
- RERA/CC/121/2022 · Sign in to download
- RERA/CC/556/2022 · Sign in to download
- 2025-Q4 · 2026-01-22
- 2025-Q3 · 2025-10-21
- 2025-Q2 · 2025-07-21
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-13
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-08-02
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2024-07-25
- 2022-Q3 · 2024-07-25
- 2022-Q2 · 2022-09-13
- 2022-Q1 · 2022-08-11
- 2021-Q4 · 2022-02-24
- 2021-Q3 · 2021-11-19
- 2021-Q2 · 2021-09-12
- 2021-Q1 · 2022-07-22
- 2020-Q4 · 2022-07-22
- 2020-Q2 · 2022-07-22
- 2020-Q1 · 2022-07-22
- 2019-Q4 · 2022-07-22
- 2019-Q3 · 2022-07-22
- 2019-Q2 · 2022-07-22