Overview
THE TECH SQUARE BY FAVOURITE HOMES
FAVOURITE CONSTRUCTIONS PRIVATE LIMITED · KAZHAKOOTTAM
Units95
Booked92 of 95
Construction progress100%As of 2023-01-09
Completion2025-12-31Proposed
Registered on2022-08-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 11 unit types |
| Construction & progress | 4 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 27 documents · 5 source links |
Registration
Registration
| Promoter | FAVOURITE CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | KAZHAKOOTTAM | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/TVM/145/2022 | |
| Registered on | 2022-08-30 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2025-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP.109/2022 | 2022-08-24 | 2027-08-23 | THIRUVANANTHAPURAM CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,116 | |
|---|---|---|
| Built-up (m²) | 16,744.41 | |
| Towers | 0 | |
| Units | 95 | |
| Booked | 92 |
Unit types
| 2BHK | 15 | 15 | THE TECH SQUARE BY FAVOURITE HOMES |
| 2BHK | 15 | 15 | THE TECH SQUARE BY FAVOURITE HOMES |
| 2BHK | 1 | 1 | THE TECH SQUARE BY FAVOURITE HOMES |
| 2BHK | 1 | 0 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 15 | 15 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 15 | 14 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 15 | 15 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 15 | 15 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 1 | 1 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 1 | 0 | THE TECH SQUARE BY FAVOURITE HOMES |
| 3BHK | 1 | 1 | THE TECH SQUARE BY FAVOURITE HOMES |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-01-09 | |
| Start | 2022-08-30 | |
| Proposed completion | 2025-12-31 |
Quarterly progress
| Quarter |
|---|
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
| 2023-2024 Q1 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2022-2023 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | FAVOURITE CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 29 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Aura Architects Engineers and Planners |
| Engineer | Aura Architects Engineers and Planners |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11081
- https://rera.kerala.gov.in/projects?district=601&page=22
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=QAYKg0EYHKvuRWvczzWVFMScR3L6hMkD7ZN9rUhYujFMwcxGxbdDJ1fIp%2F7iXk585XDMFvK%2B5zp%2BFA%2B25aVKZ%2F9%2FXnwOzW1SjPxtsEN0qodFjsFG%2FYgUk7rky9kCLDgal6KHB7I0wJZVxH1BAWB9%2B2QQThAso%2BBvDb%2BzqQ%2BK1YwSPVTXsPgk%2BQ%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11081&Division=1&UserID=30150&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2022-08-30
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-08-27
- Copy of Valid Building Permit · 2022-08-27
- Detailed technical specifications to be adopted in the project · 2022-08-27 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2022-08-25 · Sign in to download
- Site Plan / Site Map · 2022-08-25
- Site Plan / Site Map · 2022-08-27
- Other · 2022-08-27 · Sign in to download
- Other · 2022-08-27 · Sign in to download
- Other · 2022-08-27 · Sign in to download
- Clearance from Airport Authority of India · 2022-08-27 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2022-08-27 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2022-08-27 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2022-08-27 · Sign in to download
- Initial NOC from Fire and Rescue department · 2022-08-27