THE WOODS OF EAST PHASE 3

ODION BUILDERS & DEVELOPERS · Bengaluru Urban
Completion2021-09-30Revised · Proposed 2020-12-31
Registered on2019-05-04
Valid to2021-09-30
Approvals5
Complaints0

Sections

Property title & search report
Approvals5 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads
Technical report
Site & area1 site detail
Construction & progress3 progress details · 2 extensions
Developer & finance
Developer4 developer details
The evidence
Sources76 documents · 9 source links

Registration

Registration

PromoterODION BUILDERS & DEVELOPERS
DistrictBengaluru Urban
RegulatorK-RERA
Registration numberPRM/KA/RERA/1251/446/PR/190504/002541
Registered on2019-05-04
Valid to2021-09-30
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2020-12-31
Revised completion2021-09-30