DOSLHyderabad, Telangana Workspace

Overview

Timberline

Sri Srinivasa Constructions · Rajendra Nagar
Units18
Booked14 of 18
Construction progress96.5%
Completion2021-12-31Proposed
Registered on2019-07-12
Valid to2020-12-31
Approvals1

Sections

Property title & search report
Approvals1 approval
Technical report
Site & area5 site details · 18 unit types
Construction & progress2 progress details
Developer & finance
Developer3 developer details
The evidence
Sources6 documents · 5 source links

Registration

Registration

PromoterSri Srinivasa Constructions
DistrictHyderabad
LocalityRajendra Nagar
RegulatorTelangana RERA
Registration numberP02500001021
Registered on2019-07-12
Valid to2020-12-31
Project typeResidential
Status (as filed)New Project
Proposed completion2021-12-31