DOSLChhattisgarh Workspace

Overview

TIRUPATI ENCLAVE PHASE -I

KANCHAN COMPLEXES PVT LTD · RAIPUR
Units60
Booked60 of 60As of 2025-03-31
Construction progress97%As of 2025-03-31
Completion2025-02-28Revised · Proposed 2023-05-31
Registered on2018-06-05
Approvals4
Cases1

Sections

Property title & search report
Approvals4 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 21 quarters
Technical report
Site & area3 site details · 60 unit types
Construction & progress4 progress details · 21 quarters
Developer & finance
Developer3 developer details
The evidence
Sources136 documents · 10 source links

Registration

Registration

PromoterKANCHAN COMPLEXES PVT LTD
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA050618000040
Registered on2018-06-05
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2023-05-31
Revised completion2025-02-28