Overview
TN/01/Building/0194/2019
The EE & ADO · Kancheepuram
Units40
Completion2025-09-30Revised · Proposed 2020-04
Registered on2019-11-09
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 1 site detail · 1 unit type |
| Construction & progress | 2 progress details · 1 quarter · 4 extensions |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 3 documents · 3 source links |
Registration
Registration
| Promoter | The EE & ADO | |
|---|---|---|
| District | Kancheepuram | |
| Regulator | TNRERA | |
| Registration number | TN/01/Building/0194/2019 | |
| Registered on | 2019-11-09 | |
| Project type | Building | |
| Status (as filed) | Progress of Work as on June 2023 | |
| Proposed completion | 2020-04 | |
| Revised completion | 2025-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Details |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 40 |
|---|
Unit types
| Type | Units |
|---|---|
| Dwelling units | 40 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2020-04 | |
|---|---|---|
| Revised completion | 2025-09-30 |
Quarterly progress
| Quarter |
|---|
| 2023-Q2 |
Extensions
| Valid to |
|---|
| 2021-04 |
| 2022-04-30 |
| 2025-03-31 |
| 2025-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | The EE & ADO | |
|---|---|---|
| Other projects in this city pack | 1 |
Sources