DOSLTamil Nadu Workspace

Overview

TN/03/Building/0124/2020

The Executive Engineer · Cuddalore
Units288
Completion2024-12-31Revised · Proposed 2021-12
Registered on2020-03-10
Approvals1

Sections

Property title & search report
Approvals1 approval
Technical report
Site & area1 site detail · 1 unit type
Construction & progress2 progress details · 1 quarter · 1 extension
Developer & finance
Developer2 developer details
The evidence
Sources3 documents · 3 source links

Registration

Registration

PromoterThe Executive Engineer
DistrictCuddalore
RegulatorTNRERA
Registration numberTN/03/Building/0124/2020
Registered on2020-03-10
Project typeBuilding
Status (as filed)Progress of Work as on June 2021
Proposed completion2021-12
Revised completion2024-12-31