TN/25/Building/0357/2020

The Executive Engineer · Sivagangai
Units900
Completion2025-12-31Revised · Proposed 2022-12
Approvals1

Sections

Property title & search report
Approvals1 approval
Technical report
Site & area1 site detail · 1 unit type
Construction & progress2 progress details · 1 quarter · 4 extensions
Developer & finance
Developer2 developer details
The evidence
Sources3 documents · 3 source links

Registration

Registration

PromoterThe Executive Engineer
DistrictSivagangai
RegulatorTNRERA
Registration numberTN/25/Building/0357/2020
Project typeBuilding
Status (as filed)Progress of Work as on September 2025
Proposed completion2022-12
Revised completion2025-12-31