Overview
TULASI LAKE FRONT,BLOCK 9
TULASI CONSTRUCTIONS · SURARAM VILLAGE-1
Units15
Booked0 of 15
Completion2026-07-30Proposed
Registered on2021-02-01
Valid to2026-07-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 15 unit types |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 10 documents · 4 source links |
Registration
Registration
| Promoter | TULASI CONSTRUCTIONS | |
|---|---|---|
| District | Medchal-Malkajgiri | |
| Locality | SURARAM VILLAGE-1 | |
| Regulator | Telangana RERA | |
| Registration number | P02200002519 | |
| Registered on | 2021-02-01 | |
| Valid to | 2026-07-30 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2026-07-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Plan approval | 2/C26/08255/2020 | 2020-07-30 | GHMC |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 668.9 | |
|---|---|---|
| Built-up (m²) | 1,966.11 | |
| Towers | 1 | |
| Units | 15 | |
| Booked | 0 |
Unit types
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 1 |
| 2BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 1 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 1 |
| 2BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 2 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 2 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 2 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 3 |
| 2BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 3 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 3 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 4 |
| 2BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 4 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 4 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 5 |
| 2BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 5 |
| 3BHK | 1 | 0 | TULASI LAKE FRONT,BLOCK 9 | 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2026-07-30 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | TULASI CONSTRUCTIONS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rerait.telangana.gov.in/PrintPreview/PrintPreview?q=9uf%2ByKe735RfeubsIlJ8pClhmpqHRKWnDfkoTaCn2LB3nxi8s%2BvFTM%2FNCthf7mFqQaB%2Fo8TuPDHqGmBf4MOmGrKz5lgiZJNZCG4qeeKCEnqwVKGcpoU2raqNnm%2BNKzV7fuWcqqe%2FqiZlfdWPjf%2Fzw5eQfiFvlLVxrkb6uWP4T8k8wRLSfk0krQ%3D%3D
- https://rerait.telangana.gov.in/SearchList/GetShowCertificateFileContent?QueryStringID=UHJvamVjdElEPTQzMzYmRGl2aXNpb249MSZVc2VySUQ9NDEwOTQmUm9sZUlEPTEmQXBwSUQ9MTgwNTQmQWN0aW9uPVNFQVJDSCZDaGFyYWN0ZXJEPTczJkV4dEFwcElEPQ%3D%3D
- https://rerait.telangana.gov.in/SearchList/Search
- Details of encumbrances · Sign in to download
- Copy of Approval Layout Plan
- Declaration in FORM B · Sign in to download
- Commencement Certificate/Copy of Building Permit/Proceedings
- Copy of Sanctioned Building Plan
- Copy of Board Resolution for appointment of Authorized Signatory in case of other than individual · Sign in to download
- Form–1A Architects certificate Overall completion of registered project · Sign in to download
- Local Authority Completion Certificate/Occupancy Certificate doc/Final Layout Document
- Local Authority Completion Certificate/Occupancy Certificate doc/Final Layout Document
- View Certificate · 2021-02-01
- Occupancy certificate