TULIP VIOLET PHASE-II

TULIP INFRATECH PVT. LTD. · Gurugram
Completion2019-07-05Revised · Proposed 2019-12-31
Registered on2018-12-18
Valid to2020-12-31
Approvals4

Sections

Property title & search report
Approvals4 approvals
Disputes & cases2 registration details
Contract & costs3 cost heads
Technical report
Site & area2 site details · 7 unit types
Construction & progress2 progress details
Developer & finance
Developer3 developer details
The evidence
Sources13 documents · 2 source links

Registration

Registration

PromoterTULIP INFRATECH PVT. LTD.
DistrictGurugram
RegulatorHRERA Gurugram
Registration numberGGM/304/2018/36 DATED 18.12.2018
Registered on2018-12-18
Valid to2020-12-31
Status (as filed)Lapsed Project
Proposed completion2019-12-31
Revised completion2019-07-05