Overview
TURNING POINT ( GROUP HOUSING)
VATIKA LIMITED · Gurugram
Completion2025-01-30Revised · Proposed 2025-01-30
Registered on2017-09-15
Valid to2024-02-15
Approvals10
Cases4
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Disputes & cases | 4 cases · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 39 documents · 5 source links |
Registration
Registration
| Promoter | VATIKA LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 213 OF 2017 DATED 15.09.2017 | |
| Registered on | 2017-09-15 | |
| Valid to | 2024-02-15 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2025-01-30 | |
| Revised completion | 2025-01-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 91 of 2013 Dated 26.10.2013 | Town & Country Planning Department | |
| Layout Plan | 2015-05-01 | ||
| Building Plan | 2015-05-01 | ||
| I. LAY OUT PLAN | 2015-09-01 | ||
| II. ZONING PLAN | 2013-10-28 | ||
| III. BUILDING PLAN | 2015-09-01 | ||
| IV. SITE PLAN | 2015-09-01 | ||
| V. FLOOR PLAN | 2015-09-01 | ||
| VI. APARTMENT PLANS | 2015-09-01 | ||
| VII. ELEVATION SECTION | 2015-09-01 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA-GRG-5521-2019 | HRERA Gurugram | Pending |
| RERA-GRG-2807-2022 | HRERA Gurugram | |
| RERA-GRG-3274-2022 | HRERA Gurugram | Pending |
| RERA-GRG-5033-2022 | HRERA Gurugram | Pending |
Complaints & cases
| Cases | 4 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2024-02-15 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹14,80,00,000 | |
|---|---|---|
| Construction | ₹2,68,46,26,000 | |
| Total | ₹3,48,95,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 69,939.685 | |
|---|---|---|
| FAR | 175 |
Unit types
| Type |
|---|
| 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2025-01-30 | |
|---|---|---|
| Revised completion | 2025-01-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VATIKA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 13 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/assistancecontrol/print_quarterly_schedules/Mg==/NTAy/MjAxOQ==
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/MjEzIG9mIDIwMTcgZGF0ZWQgMTUuMDkuMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/1115
- https://nominatim.openstreetmap.org/search?q=sector+88b%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-09-15
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-01-31 · Sign in to download
- 1 RERA REGISTRATION CERTIFICATE OF TURNING POINT · 2020-01-31 · Sign in to download
- 4 REP II · 2020-01-31 · Sign in to download
- 5 REGISTRATION CERTIFICATE OF COMPANY · 2020-01-31 · Sign in to download
- 8 BALANCE SHEET · 2020-01-31 · Sign in to download
- 10 SHAREHOLDERS · 2020-01-31 · Sign in to download
- 27 ARCHITECT AND ENGINEER CERTIFICATE · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- 15 PROJECT DESCRIPTION AND COST · 2020-01-31 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-01-31 · Sign in to download
- 3 REP I (OLD) · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- 11 BR (AUTHORISED SIGNATORY) · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- 32 CASH FLOW STATEMENT · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- 23 DETAIL OF UNITS · 2020-01-31 · Sign in to download
- 18 SECTORIAL MAP · 2020-01-31 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-01-31
- 19 ZONING PLAN · 2020-01-31
- 7 MOA AND AOA · 2020-01-31 · Sign in to download
- 17 LOCATION PLAN · 2020-01-31
- 30 LIST OF ARCHITECT ENGINEER ETC · 2020-01-31 · Sign in to download
- 25 DETAIL OF PARKING · 2020-01-31 · Sign in to download
- 22 PROJECT REPORT · 2020-01-31 · Sign in to download
- 28 CA CERTIFICATE · 2020-01-31 · Sign in to download
- 24 ANNEXURE 3-3 (WORK PLAN) · 2020-01-31
- 21 BUILDING PLAN (BR-III) · 2020-01-31
- 29 TIME PERIOD COMMITED TO ALLOTTEE · 2020-01-31 · Sign in to download
- 31 CA CERTIFICATE (NON DEFAULT) · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- ZONING PLAN · 2020-01-31
- 33 COLLECTION STATEMENT · 2020-01-31 · Sign in to download
- 40 ADVERTISEMENT · 2020-01-31 · Sign in to download
- 26 DEVELOPMENT WORK PLAN · 2020-01-31
- 34 ENCUMBRANCES · 2020-01-31 · Sign in to download
- Other · 2020-01-31 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-01-31