Overview
TWIN TOWER
Geetanjali Real Tech Private Limited · Patna
Units153
Booked42 of 153As of 2025-12-31
Construction progress45%As of 2025-12-31
Completion2028-12-31Proposed
Registered on2022-12-23
Valid to2028-12-31
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 27 unit types |
| Construction & progress | 4 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 15 source links |
Registration
Registration
| Promoter | Geetanjali Real Tech Private Limited | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00212-5/198/R-1504/2022 | |
| Registered on | 2022-12-23 | |
| Valid to | 2028-12-31 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2028-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2022-06-07 | PATNA METROPOLITAN AREA AUTHORITY |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | ||
| Notice of Commencement in form X | ||
| Environment Clearance | ||
| Fire NOC | STATE FIRE OFFICE |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,70,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,055.05 | |
|---|---|---|
| Built-up (m²) | 6,173.73 | |
| FAR | 3 | |
| Towers | 1 | |
| Units | 153 | |
| Booked | 42 | |
| Booked as of | 2025-12-31 |
Unit types
| 2 BHK | 29 | 1 |
| 2 BHK | 10 | 1 |
| 1 BHK | 14 | 1 |
| 3 BHK | 28 | 1 |
| Shop | 1 | 1 |
| Shop | 1 | 1 |
| Shop | 1 | 1 |
| Shop | 1 | 1 |
| Shop | 7 | 1 |
| Shop | 4 | 1 |
| Shop | 7 | 1 |
| Shop | 1 | 1 |
| Shop | 3 | 1 |
| Shop | 1 | 1 |
| Shop | 1 | 1 |
| Shop | 1 | 1 |
| Shop | 5 | 1 |
| Shop | 2 | 1 |
| Shop | 2 | 1 |
| Shop | 5 | 1 |
| Shop | 4 | 1 |
| Shop | 2 | 1 |
| Shop | 2 | 1 |
| Shop | 6 | 1 |
| Shop | 6 | 1 |
| Shop | 4 | 1 |
| Shop | 5 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 45% | |
|---|---|---|
| As of | 2025-12-31 | |
| Start | 2022-12-02 | |
| Proposed completion | 2028-12-31 |
Quarterly progress
| 2025-Q4 | 2026-01-15 | 45% | 42 |
| 2025-Q3 | 2025-10-15 | ||
| 2025-Q1 | 2025-04-13 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2025-01-14 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Geetanjali Real Tech Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP233201800212-5
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP233201800212&ld=pan&pj=RERAP233201800212-5&f=2025-2026&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP233201800212-5
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-15
- Quarterly Progress Image · 2025-10-15
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-15
- Q4-Jan to Mar / 2024-2025 · 2025-04-13
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2025-01-14
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-12
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2025-Q3 · 2025-10-15
- 2025-Q1 · 2025-04-13
- 2024-Q3 · 2024-10-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2025-01-14
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-12