Overview
UCHDPL-Sector-5-Wave Floors
UPPAL CHADHA HI-TECH DEVELOPERS PVT. LTD. · Ghaziabad
Units39
Completion2021-04-29Revised · Proposed 2019-10-31
Registered on2017-07-28
Valid to2021-04-29
Approvals1
Complaints74As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 74 project complaints · 1,056 promoter complaints |
| Technical report | |
| Site & area | 4 site details · 8 unit types |
| Construction & progress | 3 progress details · 5 quarters · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 37 documents · 12 source links |
Registration
Registration
| Promoter | UPPAL CHADHA HI-TECH DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ3790 | |
| Registered on | 2017-07-28 | |
| Valid to | 2021-04-29 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2019-10-31 | |
| Revised completion | 2021-04-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 53/MP/05/ZONE-05/2015-16 | 2015-05-15 | 2021-10-17 | Ghaziabad Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 74 | |
|---|---|---|
| Promoter | 1,056 | |
| As of | 2026-10-29 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,179 | |
|---|---|---|
| Towers | 2 | |
| Maximum floors | 2 | |
| Units | 39 |
Unit types
| 2 BHK | 56.071 | 1 | 112.5 | GF |
| 2 BHK | 56.78 | 1 | 112.5 | 1 |
| 2 BHK | 53.694 | 1 | 112.5 | 2 |
| OTHER | 0 | 112.5 | GF | |
| OTHER | 0 | 162 | GF | |
| 2 BHK | 88.171 | 12 | 162 | GF |
| 2 BHK | 86.587 | 12 | 162 | 1 |
| 2 BHK | 76.145 | 12 | 162 | 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-07-31 | |
|---|---|---|
| Proposed completion | 2019-10-31 | |
| Revised completion | 2021-04-29 |
Quarterly progress
| Quarter |
|---|
| 2020-Q2 |
| 2020-Q3 |
| 2020-Q4 |
| 2021-Q1 |
| 2021-Q2 |
Extensions
| Valid to | Reason |
|---|---|
| 2020-10-30 | |
| 2021-04-29 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | UPPAL CHADHA HI-TECH DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES BANK LTD | |
| Other projects in this city pack | 31 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=39tNWu82caA=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=YbjNg7/AzX7cCn+Yg8aCqRuyPBTPVnqxg43tRX/wVw4=&PaURJEMAN4=ZL9MNERkNdY0We3vyHHTMQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=39tNWu82caA=
- Commencement Certificate · 2018-07-16
- Waste Disposal Plan · 2018-06-02
- Water Supply Plan · 2018-07-16
- Electricity Supply Plan · 2018-07-16
- Development Work Plan · 2018-07-16
- CA CERTIFICATE · 2018-07-06 · Sign in to download
- ARCHITECT CERTIFICATE · 2018-07-04 · Sign in to download
- ENGINEERS CERTIFICATE · 2018-06-01 · Sign in to download
- Other Plan(If Any) · 2017-07-28
- Other Plan(If Any) · 2017-07-28
- Other Plan(If Any) · 2017-07-28
- Other Plan(If Any) · 2017-07-28
- Development Work Plan · 2017-10-27
- Sanctioned Layout Plan (Of Entire Project) · 2017-10-27
- Other Plan(If Any) · 2017-10-27
- Authentic copy of Approval of Project · 2017-10-27
- Commencement Certificate · 2017-10-27
- Commencement Certificate · 2017-10-27
- Other Plan(If Any) · 2017-10-27
- Water Supply Plan · 2017-10-27
- Electricity Supply Plan · 2017-10-27
- Other Plan(If Any) · 2018-01-23
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2020-Q2
- 2020-Q3
- 2020-Q4
- 2021-Q1
- 2021-Q2