No survey sketch is listed on this phase's MahaRERA filing
Not verified yet: Title opinion; Records searched to; Charges on the land; Landowner share of sales; How the land reached this project; Title report; Boundary schedule; Encumbrance certificate; Sketch, sanction and mutation; Survey plots · cadastral; Land record; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
Approvals
Is it approved for its use?
RERA extensionsNone on the filingFiling read 29 Oct 2026
Permits
Approval letters
Building plan approval
2 filed · latest filed 31 Mar 2026
RERA
MahaRERA
RERA extensions
None on the filing
RERA completion date
31 Mar 2026
Disputes & cases
Are there court cases or buyer complaints on this project?
Builder: UNIQUE SHANTI DEVELOPERS LLP
Court cases on the project's land
0 cases
The filing names no land owners, so there is no name to search.
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
None listed.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Buyer complaints filed with MahaRERA on this project
0 cases
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None listed.
Buyer complaints on other projects by this builder
0 cases
9 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None listed.
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Registered: its first quarterly return is still to come
Work left
By component
Registered: its first quarterly return is still to come
Quarterly return
Registered: its first quarterly return is still to come
Dates
Dates
Developer
Can the developer deliver?
Review1 to review
Cost left₹7.93 CrEstimated ₹53.53 Cr less incurred ₹45.60 Cr
Sold5 / 48MahaRERA register
Sold in the latest quarterFirst return due
Funding
Estimated cost
Loan & collateral
Can it be financed?
Developer's project loanNo borrowed fundsBorrowed funds filed with MahaRERA
Conditions
Collateral checks
Developer's project loan
No borrowed funds
Building plan
Approval filed with MahaRERA · latest 31 Mar 2026
Stage
Certified progress
Registered: its first quarterly return is still to come
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of; Escrow bank.
Data room
Documents filed for this project
Documents filed9On MahaRERA
Available111% of filed
MahaRERA only8
Approvals with a validity dateNone read
Quarterly certificates
Filed 2026-04-23Available
Filed 2025-01-16Sign in to download
Filed 2025-04-19Sign in to download
Filed 2025-07-19Sign in to download
Filed 2025-07-19Sign in to download
Source: MahaRERA project page and the documents filed there, as read by us. 43 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
Registration certificates
Registration number
P51800051237
Registered
8 Jun 2023
Not verified yet: Building plan, Land conversion, Validity, Power NOC, Fire NOC, Environmental clearance, Airport height NOC, Pollution board (CFE), Conversion order.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
1
–
1,690–1,690 sq ft · 157.0–157.0 sq m
2
1
1
–
1,847–2,020 sq ft · 171.6–187.7 sq m
2
0
0
–
4,176 sq ft · 387.99 sq m
1
1
0
–
4,557 sq ft · 423.35 sq m
1
0
1
–
By building
Building
Units filed
Sold
Median ₹/sq ft carpet
B-Wing
25
5
₹36,539
A-Wing
23
1
–
Floor plans, brochure
No floor plans on file
Unsold stock
Unsold units
Carpet area
Unsold units
Carpet area, total
229–573 sq ft · 21.3–53.2 sq m
2
671 sq ft
684–991 sq ft · 63.6–92.0 sq m
5
3,727 sq ft
1,093–1,271 sq ft · 101.5–118.1 sq m
1
1,093 sq ft
1,690–1,690 sq ft · 157.0–157.0 sq m
1
1,690 sq ft
4,557 sq ft · 423.35 sq m
1
4,557 sq ft
All unsold
10
11,738 sq ft
Not verified yet: Recent price, super built-up; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; Mumbai, Maharashtra, past year; Mumbai, Maharashtra since 2022; This project vs Mumbai, Maharashtra; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Nearest 12 with filed prices; This project vs the nearest with filed prices; Median rent, 3 km; Rents and yields; Months to sell unsold stock; MahaRERA inventory.
Nearest mapped waterway or drain
about 0.5 km from the locality centre, drain
Nearest mapped inland water body
about 0.5 km from the locality centre, an unnamed water body
Around it
Distances
Approximate: locality level
Basemap: Esri, OpenStreetMap contributors
Map centred on the locality the filing names, approximate: locality level. The filing names only the locality. The marker is its centre and the ring is 5 km; it does not mark the site.
Locality only filed: no distance from the site to show
Mapped nuisances · OpenStreetMap
Landfill or waste transfer station
about 2 km from the locality centre
Sewage treatment plant
about 1 km from the locality centre
Quarry
None mapped within 3 km of the locality centre
Crematorium
None mapped within 3 km of the locality centre
Prison
None mapped within 3 km of the locality centre
Not verified yet: Groundwater; Water supply, as filed; Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Drains and lakes; Specification and Form 5; Water at a glance; Ground level; Metro, under construction; Road distance from the site; Six city anchors · OSRM, no traffic.
Filed dates
RERA completion date
31 Mar 2026
Registered
8 Jun 2023
Certificates
Engineer, architect and fire certificates
Architect's certificate, Form 1
5 filed · latest filed 23 Apr 2026
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Schedule end; What the promoter specified · not an inspection; Specification sheet, page 1; Specification sheet · brands "or equivalent"; Structural engineer, quarterly; Design consultants (Form 6); Fire safety; Environmental clearance.
Land · ₹27.25 Cr 50.9%Development · ₹26.28 Cr 49.1%
Form 4
Estimated cost, at registration
₹53.53 Cr
Sales
Sold vs unsold
Sold 33.3%Unsold 66.7%
Sold per quarter
Registered: its first quarterly return is still to come
MahaRERA inventory
Units filed
48
Sold
5 · 10%
Unsold
10
Compliance
Escrow
Registered: its first quarterly return is still to come
Escrow and filings
Escrow balance
₹0 (INR)
Filed withdrawal amount
₹15,20,31,364 (INR)
Track record
Average schedule slip
DOSL builder track
MahaRERA registrations under this promoter
10
Marked completed
0
Past promised date, not completed
9
!Review
Other phases under this promoter name
9
With a filed extension or completion
5 (0 completed, 5 extended)
Average schedule slip
23 months
Not verified yet: Receivable, sold units; Cost left vs buyer dues; Cost incurred; Cost left; Collected from buyers; Land cost revision; Escrow bank; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid.