Overview
UPREM APARTMENT
Srisatya Sai Homes Pvt. Ltd. · Patna
Units32
Booked15 of 32As of 2026-06-30
Construction progress88%As of 2026-06-30
Completion2027-12-25Proposed
Registered on2023-01-27
Valid to2027-12-25
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 28 documents · 20 source links |
Registration
Registration
| Promoter | Srisatya Sai Homes Pvt. Ltd. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00396-3/228/R-1524/2023 | |
| Registered on | 2023-01-27 | |
| Valid to | 2027-12-25 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-12-25 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2022-12-11 | DANAPUR NAGAR PARISHAD | |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | |||
| Notice of Commencement in form X | |||
| Environment Clearance | 2025-01-01 | ||
| Fire NOC | 2027-09-12 | DIRECTOR-CUM-STATE FIRE OFFICER, BIHAR, PATNA | |
| Airport NOC | 2025-01-01 | ||
| Water Supply Permission | 2025-01-01 | ||
| Other approval | 2025-01-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,62,51,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,332.8 | |
|---|---|---|
| Built-up (m²) | 3,264.71 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 32 | |
| Booked | 15 | |
| Booked as of | 2026-06-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 8 | UPREM APARTMENT |
| 3 BHK | 24 | UPREM APARTMENT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 88% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2022-12-12 | |
| Proposed completion | 2027-12-25 |
Quarterly progress
| 2026-Q2 | 2026-07-30 | 88% | 15 |
| 2026-Q1 | 2026-05-05 | ||
| 2025-Q4 | 2026-02-07 | ||
| 2025-Q3 | 2025-11-03 | ||
| 2025-Q2 | 2025-08-09 | ||
| 2025-Q1 | 2025-04-21 | ||
| 2024-Q4 | 2025-01-24 | ||
| 2024-Q3 | 2024-10-12 | ||
| 2024-Q2 | 2024-08-12 | ||
| 2024-Q1 | 2024-08-12 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Srisatya Sai Homes Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP125201800396-3
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP125201800396&ld=pan&pj=RERAP125201800396-3&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP125201800396-3
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-30
- Quarterly Progress Image · 2025-08-09
- Q4 (Jan - Mar) / 2025-2026 · 2026-05-05
- Q3 (Oct - Dec) / 2025-2026 · 2026-02-07
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-03
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-09
- Q4-Jan to Mar / 2024-2025 · 2025-04-21
- Q3-Oct to Dec / 2024-2025 · 2025-01-24
- Q2-Jul to Sep / 2024-2025 · 2024-10-12
- Q1-Apr to Jun / 2024-2025 · 2024-08-12
- Q4-Jan to Mar / 2023-2024 · 2024-08-12
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q1 · 2026-05-05
- 2025-Q4 · 2026-02-07
- 2025-Q3 · 2025-11-03
- 2025-Q2 · 2025-08-09
- 2025-Q1 · 2025-04-21
- 2024-Q4 · 2025-01-24
- 2024-Q3 · 2024-10-12
- 2024-Q2 · 2024-08-12
- 2024-Q1 · 2024-08-12
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25