Overview
URBAN ESTATE
M/S SMART HOMES · RAIPUR
Units19
Booked9 of 19As of 2026-06-30
Construction progress87%As of 2026-06-30
Completion2027-02-28Revised · Proposed 2025-10-31
Registered on2023-01-24
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 14 quarters |
| Technical report | |
| Site & area | 3 site details · 19 unit types |
| Construction & progress | 4 progress details · 14 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 84 documents · 6 source links |
Registration
Registration
| Promoter | M/S SMART HOMES | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA240123001595 | |
| Registered on | 2023-01-24 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2025-10-31 | |
| Revised completion | 2027-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,03,96,000 | |
|---|---|---|
| Construction | ₹2,24,63,000 |
Quarterly money flows
| 2023-Q1 | ₹7,33,460 |
| 2023-Q2 | ₹16,78,460 |
| 2023-Q3 | ₹15,05,328 |
| 2023-Q4 | ₹32,88,244 |
| 2024-Q1 | ₹17,88,244 |
| 2024-Q2 | ₹18,85,544 |
| 2024-Q3 | ₹8,74,544 |
| 2024-Q4 | ₹9,09,544 |
| 2025-Q1 | ₹2,14,615 |
| 2025-Q2 | ₹2,14,615 |
| 2025-Q3 | ₹9,23,575 |
| 2025-Q4 | ₹21,73,775 |
| 2026-Q1 | ₹4,45,375 |
| 2026-Q2 | ₹95,375 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 19 | |
|---|---|---|
| Booked | 9 | |
| Booked as of | 2026-06-30 |
Unit types
| Smart Homes- Urban Estate-1 | 1 | 1 |
| Smart Homes- Urban Estate-2 | 1 | 1 |
| Smart Homes- Urban Estate-3 | 1 | 1 |
| Smart Homes- Urban Estate-4 | 1 | 0 |
| Smart Homes- Urban Estate-5 | 1 | 0 |
| Smart Homes- Urban Estate-6 | 1 | 0 |
| Smart Homes- Urban Estate-7 | 1 | 0 |
| Smart Homes- Urban Estate-8 | 1 | 0 |
| Smart Homes- Urban Estate-9 | 1 | 0 |
| Smart Homes- Urban Estate-10 | 1 | 1 |
| Smart Homes- Urban Estate-11 | 1 | 1 |
| Smart Homes- Urban Estate-12 | 1 | 1 |
| Smart Homes- Urban Estate-13 | 1 | 0 |
| Smart Homes- Urban Estate-14 | 1 | 0 |
| Smart Homes- Urban Estate-15 | 1 | 1 |
| Smart Homes- Urban Estate-16 | 1 | 1 |
| Smart Homes- Urban Estate-17 | 1 | 1 |
| Smart Homes- Urban Estate-18 | 1 | 0 |
| Smart Homes- Urban Estate-19 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 87% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2025-10-31 | |
| Revised completion | 2027-02-28 |
Quarterly progress
| 2023-Q1 | 1% |
| 2023-Q2 | 14% |
| 2023-Q3 | 31% |
| 2023-Q4 | 46% |
| 2024-Q1 | 53% |
| 2024-Q2 | 64% |
| 2024-Q3 | 64% |
| 2024-Q4 | 64% |
| 2025-Q1 | 73% |
| 2025-Q2 | 84% |
| 2025-Q3 | 84% |
| 2025-Q4 | 84% |
| 2026-Q1 | 84% |
| 2026-Q2 | 87% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S SMART HOMES | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTk0Nw==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities