Overview
URBAN HOMES-II EXTENSION
PYRAMID INFRATECH PRIVATE LIMITED · Gurugram
Units188
Completion2023-11-15Proposed
Registered on2020-09-28
Valid to2023-11-15
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 51 documents · 3 source links |
Registration
Registration
| Promoter | PYRAMID INFRATECH PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/412/144/2020/28 DATED 28.09.2020 | |
| Registered on | 2020-09-28 | |
| Valid to | 2023-11-15 | |
| Status (as filed) | Registered | |
| Proposed completion | 2023-11-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 78 OF 2018 DATED 17.11.2018 | Town & Country Planning Department | |
| Layout Plan | 2020-06-15 | ||
| Building Plan | 2020-06-15 | ||
| I. ZONING PLAN APPROVAL VIDE NO. 6966 | 2018-11-22 | ||
| II. SERVICE PLAN ESTIMATES APPROVAL VIDE MEMO NO.87402 | 2020-06-18 | ||
| III. BUILDING PLAN MEMO NO. ZP-1068/AD(RA)/2020/9927 | 2020-06-15 | ||
| IV. LICENSE 78 OF 2018 | 2018-11-17 | ||
| V. AIRPORT HEIGHT CLEARANCE VIDE NO. PALM/NORTH/B/012419/366326 | 2019-01-19 | ||
| VI. ENVIRONMENT CLEARANCE VIDE NO. SIA/HR/MIS/156710/2020 | 2020-06-09 | ||
| VII. FIRE SCHEME APPROVAL FS/2020/188 DATED 04.08.2020 | 2020-03-02 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹8,92,31,000 | |
|---|---|---|
| Construction | ₹22,80,11,000 | |
| Total | ₹42,50,22,999.99999994 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 188 |
|---|
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 59.797 | 92 |
| Apartment/Shops/Other Buildings | 59.946 | 96 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-11-15 | |
|---|---|---|
| Proposed completion | 2023-11-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PYRAMID INFRATECH PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1399
- https://nominatim.openstreetmap.org/search?q=sector+86%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2020-09-28
- CA CERTIFICATE FOR REP I · 2020-07-22 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2020-07-22 · Sign in to download
- EDC II · 2020-07-22 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-07-22 · Sign in to download
- DEMARCATION PLAN · 2020-07-21
- ANNUAL REPORT 2019 · 2020-07-22 · Sign in to download
- BR III · 2020-07-22 · Sign in to download
- CA CERTIFICATE OF PROMOTER · 2020-07-22 · Sign in to download
- TREE CUTTING AFFIDAVIT · 2020-07-22 · Sign in to download
- JAMABANDI · 2020-07-22 · Sign in to download
- MOA & AOA · 2020-07-22 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-07-21
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2020-07-21 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-07-21
- BANK UNDERTAKING · 2020-07-22 · Sign in to download
- DD · 2020-07-22 · Sign in to download
- LICENSE ENTRY IN REVENUE RECORD · 2020-07-22
- BANK AFFIDAVIT · 2020-07-22 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-07-21 · Sign in to download
- ANNUAL REPORT 2017 · 2020-07-22 · Sign in to download
- NOC DRINKING WATER · 2020-07-22
- PROJECT REPORT · 2020-07-22 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2020-07-21 · Sign in to download
- LETTER DEMARCATION PLAN · 2020-07-22
- NOC HEIGHT CLEARANCE · 2020-07-22
- SERVICE ESTIMATE · 2020-07-22 · Sign in to download
- SUPERIMPOSED DEMARCATION · 2020-07-22 · Sign in to download
- FIRE ACKNOWLEDGEMENT SLIP · 2020-07-22 · Sign in to download
- GPA · 2020-07-22 · Sign in to download
- ZONING PLAN · 2020-07-21
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2020-07-22
- BOARD RESOLUTION FOR BANK · 2020-07-22 · Sign in to download
- ANNUAL REPORT 2018 · 2020-07-22 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-07-21
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-07-22
- ENVIRONMENT ACKNOWLEDGEMENT SLIP · 2020-07-22 · Sign in to download
- LOI · 2020-07-22 · Sign in to download
- SEARCH REPORT · 2020-07-22 · Sign in to download
- NOC SEWERAGE CONNECTION · 2020-07-22
- EDC I · 2020-07-22 · Sign in to download
- LC IV · 2020-07-22 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-07-22 · Sign in to download
- NOC ARAWALI · 2020-07-22
- COLLABORATION AGREEMENT · 2020-07-22 · Sign in to download
- NOC FOREST · 2020-07-22
- NOC STP WATER · 2020-07-22
- SIJRA · 2020-07-22 · Sign in to download
- PERT CHART · 2020-07-22 · Sign in to download
- POWER ASSURANCE CERTIFICATE · 2020-07-22 · Sign in to download
- Occupation Certificate · 2024-09-06 · Sign in to download