Overview
Urbana Square
AGI Infra Limited · Jalandhar
Units360
Completion2027-09-01Proposed
Valid to2027-09-01
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 15 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 42 documents · 19 source links |
Registration
Registration
| Promoter | AGI Infra Limited | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PC0397 | |
| Valid to | 2027-09-01 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-09-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2025-10-28 |
| CLU Certificate | |
| Electric Substation NOC | 2025-05-08 |
| Environment Clearance certificate/ NOC | 2024-07-27 |
| Environment Clearance certificate/ NOC | 2024-07-27 |
| License to develop colony or society from Competent Authority | |
| NOC from NHAI/ PWD | 2021-08-23 |
| Other Document (Affidavit regarding submission of NOCs) | 2025-09-22 |
| Other Document (Drainage NOC) | 2022-02-28 |
| Other Document (Forest NOC) | 2025-11-08 |
| Other Document (Forest NOC) | 2022-08-22 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-03-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹61,57,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 12,451.93 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 5 | |
| Units | 360 |
Unit types
| Shop No. 1 to 41(Ground Floor) | 65.03 | 41 | URBANA SQUARE |
| Shop No. 44 to 45(Ground Floor) | 24.06 | 2 | URBANA SQUARE |
| Shop No. 46 to 50, 60 to 82(Ground Floor) | 39.34 | 28 | URBANA SQUARE |
| Shop No. 1 to 41(First Floor) | 65.03 | 41 | URBANA SQUARE |
| Shop No. 44 to 45(First Floor) | 24.06 | 2 | URBANA SQUARE |
| Shop No. 46 to 50, 60 to 82(First Floor) | 39.34 | 28 | URBANA SQUARE |
| Office No. 1 to 41, 27-A, 27-B(Second Floor) | 65.03 | 43 | URBANA SQUARE |
| Office No. 42 to 43(Second Floor) | 24.06 | 2 | URBANA SQUARE |
| Office No. 46 to 50, 60 to 82(Second Floor) | 39.34 | 28 | URBANA SQUARE |
| Office No. 1 to 41, 27-A, 27-B(Third Floor) | 65.03 | 43 | URBANA SQUARE |
| Office No. 44 to 45(Third Floor) | 24.06 | 2 | URBANA SQUARE |
| Office No. 46 to 50, 60 to 82(Third Floor) | 39.34 | 28 | URBANA SQUARE |
| Office No. 1 to 41, 27-A, 27-B(Fourth Floor) | 55.92 | 43 | URBANA SQUARE |
| Office No. 44 to 45(Fourth Floor) | 18.85 | 2 | URBANA SQUARE |
| Office No. 46 to 50, 61 to 82(Fourth Floor) | 30.23 | 27 | URBANA SQUARE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-11-02 | |
|---|---|---|
| Proposed completion | 2027-09-01 |
Quarterly progress
| 2025-Q4 | 2026-01-15 |
| 2026-Q1 | 2026-04-15 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AGI Infra Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 4 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | LIVEHOOAH TECHNOLOGIES PRIVATE LIMITED |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12497&inPromoter_ID=2996&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-10-28
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-05-08
- Environment Clearance certificate/ NOC · 2024-07-27
- Environment Clearance certificate/ NOC · 2024-07-27
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2021-08-23
- Other Document (Clar. regd. diff. in area and inventory in EC) · 2025-11-15 · Sign in to download
- Other Document (Disposal of Sewerage Treated Waste Water) · 2024-07-09 · Sign in to download
- Other Document (Drainage NOC) · 2022-02-28
- Other Document (Forest NOC) · 2025-11-08
- Other Document (Forest NOC) · 2022-08-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-28
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-10-28
- CLU Certificate
- Electric Substation NOC · 2025-05-08
- Environment Clearance certificate/ NOC · 2024-07-27
- Environment Clearance certificate/ NOC · 2024-07-27
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2021-08-23
- Other Document (Affidavit regarding submission of NOCs) · 2025-09-22
- Other Document (Drainage NOC) · 2022-02-28
- Other Document (Forest NOC) · 2025-11-08
- Other Document (Forest NOC) · 2022-08-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-28
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-04-15
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-14