Overview
Uttam Shyamashish Park
Galaxy Mining Private Limited · Jaipur
Units342
Booked241 of 342As of 2025-12-31
Completion2027-07-31Revised · Proposed 2024-07-01
Registered on2024-07-31
Valid to2027-07-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 207 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 227 documents · 6 source links |
Registration
Registration
| Promoter | Galaxy Mining Private Limited | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/3206 | |
| Registered on | 2024-07-31 | |
| Valid to | 2027-07-31 | |
| Project type | Plotted | |
| Status (as filed) | INPROGRESS | |
| Proposed completion | 2024-07-01 | |
| Revised completion | 2027-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹21,64,72,380 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹33,64,72,380 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q4 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 99,778.6 | |
|---|---|---|
| Built-up (m²) | 42,581.16 | |
| Towers | 342 | |
| Units | 342 | |
| Booked | 241 | |
| Booked as of | 2025-12-31 |
Unit types
| PLOT NO. E-01 TO E-13 | 13 | 5 |
| PLOT NO. E-14 TO E-22 | 9 | 6 |
| PLOT NO. E-23 | 1 | 0 |
| PLOT NO. E-24 | 1 | 0 |
| PLOT NO. E-25 | 1 | 1 |
| PLOT NO. E-26 | 1 | 1 |
| PLOT NO. E-27 | 1 | 1 |
| PLOT NO. E-28 | 1 | 1 |
| PLOT NO. E-29 | 1 | 1 |
| PLOT NO. E-30 | 1 | 0 |
| PLOT NO. E-31 | 1 | 1 |
| PLOT NO. E-32 | 1 | 0 |
| PLOT NO. E-33 | 1 | 0 |
| PLOT NO. E-34 | 1 | 0 |
| PLOT NO. L-12 | 1 | 1 |
| PLOT NO. L-17 | 1 | 1 |
| PLOT NO. L-13 | 1 | 1 |
| PLOT NO. L-10 | 1 | 1 |
| PLOT NO. L-24 | 1 | 0 |
| PLOT NO. L-33 | 1 | 1 |
| PLOT NO. L-32 | 1 | 0 |
| PLOT NO. L-09 | 1 | 0 |
| PLOT NO. L-31 | 1 | 1 |
| PLOT NO. L-23 | 1 | 0 |
| PLOT NO. L-34 | 1 | 0 |
| PLOT NO. L-14 | 1 | 1 |
| PLOT NO. L-29 | 1 | 0 |
| PLOT NO. L-27 | 1 | 1 |
| PLOT NO. L-06 | 1 | 1 |
| PLOT NO. L-16 | 1 | 1 |
| PLOT NO. L-21 | 1 | 0 |
| PLOT NO. L-20 | 1 | 0 |
| PLOT NO. L-22 | 1 | 1 |
| PLOT NO. L-07 | 1 | 1 |
| PLOT NO. L-26 | 1 | 0 |
| PLOT NO. L-08 | 1 | 1 |
| PLOT NO. L-30 | 1 | 1 |
| PLOT NO. L-11 | 1 | 1 |
| PLOT NO. L-18 | 1 | 1 |
| PLOT NO. L-19 | 1 | 0 |
| PLOT NO. L-15 | 1 | 1 |
| PLOT NO. L-25 | 1 | 0 |
| PLOT NO. L-28 | 1 | 1 |
| PLOT NO. L-01 TO L-05 | 5 | 3 |
| PLOT NO. 170 | 1 | 1 |
| PLOT NO. 171 | 1 | 1 |
| PLOT NO. 97 TO 106, 136 TO 148, 151 TO 163, 221 TO 228 | 44 | 44 |
| PLOT NO. 169 | 1 | 1 |
| PLOT NO. 172 | 1 | 1 |
| PLOT NO. 168 | 1 | 1 |
| PLOT NO. 173 | 1 | 1 |
| PLOT NO. 167 | 1 | 1 |
| PLOT NO. 174 | 1 | 1 |
| PLOT NO. 166 | 1 | 1 |
| PLOT NO. 175 | 1 | 1 |
| PLOT NO. 176 | 1 | 1 |
| PLOT NO. 177 | 1 | 1 |
| PLOT NO. 178 | 1 | 1 |
| PLOT NO. 179 | 1 | 1 |
| PLOT NO. 180 | 1 | 1 |
| PLOT NO. 199 | 1 | 1 |
| PLOT NO. 198 | 1 | 1 |
| PLOT NO. 200 | 1 | 1 |
| PLOT NO. 197 | 1 | 1 |
| PLOT NO. 196 | 1 | 1 |
| PLOT NO. 195 | 1 | 1 |
| PLOT NO. 194 | 1 | 1 |
| PLOT NO. 201 | 1 | 1 |
| PLOT NO. 119 TO 129, 183 TO 191, 212 TO 218 | 27 | 27 |
| PLOT NO. 202 | 1 | 1 |
| PLOT NO. 203 | 1 | 1 |
| PLOT NO. 204 | 1 | 1 |
| PLOT NO. 205 | 1 | 1 |
| PLOT NO. 206 | 1 | 1 |
| PLOT NO. 207 | 1 | 1 |
| PLOT NO. 208 | 1 | 1 |
| PLOT NO. 209 | 1 | 1 |
| PLOT NO. 90 | 1 | 1 |
| PLOT NO. 01 | 1 | 1 |
| PLOT NO. 58 | 1 | 1 |
| PLOT NO. 51 | 1 | 1 |
| PLOT NO. 57 | 1 | 1 |
| PLOT NO. 52 | 1 | 1 |
| PLOT NO. 56 | 1 | 1 |
| PLOT NO. 55 | 1 | 1 |
| PLOT NO. 53 | 1 | 1 |
| PLOT NO. 54 | 1 | 1 |
| PLOT NO. 229 | 1 | 1 |
| PLOT NO. 76 | 1 | 1 |
| PLOT NO. 149 | 1 | 1 |
| PLOT NO. 77 | 1 | 1 |
| PLOT NO. 193 | 1 | 1 |
| PLOT NO. 62 TO 68 | 7 | 7 |
| PLOT NO. 91 | 1 | 1 |
| PLOT NO. 78, 79, 88, 89 | 4 | 3 |
| PLOT NO. 94 | 1 | 0 |
| PLOT NO. 192 & 211 | 2 | 1 |
| PLOT NO. 96 | 1 | 0 |
| PLOT NO. 09 | 1 | 1 |
| PLOT NO. 07, 08, 10, 14, 80, 81, 82, 85, 86, 87 | 10 | 10 |
| PLOT NO. 71 | 1 | 1 |
| PLOT NO. 92 | 1 | 1 |
| PLOT NO. 72 | 1 | 1 |
| PLOT NO. 73 | 1 | 1 |
| PLOT NO. 74 | 1 | 1 |
| PLOT NO. 75 | 1 | 1 |
| PLOT NO. 256 TO 266 | 11 | 11 |
| PLOT NO. 02 | 1 | 1 |
| PLOT NO. 59 | 1 | 1 |
| PLOT NO. 182 | 1 | 1 |
| PLOT NO. 268 | 1 | 1 |
| PLOT NO. 165 | 1 | 1 |
| PLOT NO. 181 | 1 | 1 |
| PLOT NO. 50 | 1 | 1 |
| PLOT NO. 118 | 1 | 1 |
| PLOT NO. 12 | 1 | 1 |
| PLOT NO. 150 | 1 | 1 |
| PLOT NO. 15 | 1 | 1 |
| PLOT NO. 135 | 1 | 1 |
| PLOT NO. 132 & 133 | 2 | 2 |
| PLOT NO. 16 | 1 | 1 |
| PLOT NO. 220 | 1 | 1 |
| PLOT NO. 69 | 1 | 1 |
| PLOT NO. 131 | 1 | 1 |
| PLOT NO. 17 | 1 | 1 |
| PLOT NO. 164 | 1 | 1 |
| PLOT NO. 03 | 1 | 1 |
| PLOT NO. 83 | 1 | 1 |
| PLOT NO. 70 | 1 | 1 |
| PLOT NO. 48 | 1 | 0 |
| PLOT NO. 60 | 1 | 1 |
| PLOT NO. 49 | 1 | 1 |
| PLOT NO. 267 | 1 | 1 |
| PLOT NO. 13 | 1 | 1 |
| PLOT NO. 18 | 1 | 1 |
| PLOT NO. 04 | 1 | 1 |
| PLOT NO. 130 | 1 | 0 |
| PLOT NO. 134 | 1 | 1 |
| PLOT NO. 47 | 1 | 1 |
| PLOT NO. 06 | 1 | 1 |
| PLOT NO. 35 | 1 | 1 |
| PLOT NO. 11 | 1 | 0 |
| PLOT NO. 26 | 1 | 1 |
| PLOT NO. 25 | 1 | 0 |
| PLOT NO. 24 | 1 | 1 |
| PLOT NO. 27 | 1 | 1 |
| PLOT NO. 23 | 1 | 1 |
| PLOT NO. 28 | 1 | 1 |
| PLOT NO. 34 | 1 | 1 |
| PLOT NO. 22 | 1 | 1 |
| PLOT NO. 29 | 1 | 1 |
| PLOT NO. 21 | 1 | 0 |
| PLOT NO. 32 | 1 | 1 |
| PLOT NO. 20 | 1 | 0 |
| PLOT NO. 30 | 1 | 1 |
| PLOT NO. 19 | 1 | 0 |
| PLOT NO. 31 | 1 | 1 |
| PLOT NO. 33 | 1 | 1 |
| PLOT NO. 36 | 1 | 1 |
| PLOT NO. 37 | 1 | 0 |
| PLOT NO. 38 | 1 | 0 |
| PLOT NO. 39 | 1 | 0 |
| PLOT NO. 46 | 1 | 1 |
| PLOT NO. 45 | 1 | 1 |
| PLOT NO. 44 | 1 | 1 |
| PLOT NO. 43 | 1 | 0 |
| PLOT NO. 40 | 1 | 1 |
| PLOT NO. 42 | 1 | 1 |
| PLOT NO. 41 | 1 | 1 |
| PLOT NO. 05 | 1 | 1 |
| PLOT NO. C-01 | 1 | 1 |
| INFORMAL COMMERCIAL | 1 | 0 |
| PLOT NO. SC-01 | 1 | 1 |
| PLOT NO. SC-02 | 1 | 1 |
| PLOT NO. SC-03 | 1 | 1 |
| PLOT NO. SC-04 | 1 | 1 |
| PLOT NO. 238 | 1 | 1 |
| PLOT NO. 237 | 1 | 1 |
| PLOT NO. 236 | 1 | 1 |
| PLOT NO. 235 | 1 | 1 |
| PLOT NO. 107 | 1 | 1 |
| PLOT NO. 234 | 1 | 1 |
| PLOT NO. 241 TO 253 | 13 | 13 |
| PLOT NO. 233 | 1 | 1 |
| PLOT NO. 232 | 1 | 1 |
| PLOT NO. 239 | 1 | 1 |
| PLOT NO. 231 | 1 | 1 |
| PLOT NO. 61 | 1 | 1 |
| PLOT NO. 254 | 1 | 1 |
| PLOT NO. 240 | 1 | 1 |
| PLOT NO. 109 | 1 | 1 |
| PLOT NO. 110 | 1 | 1 |
| PLOT NO. 111 | 1 | 1 |
| PLOT NO. 116 | 1 | 1 |
| PLOT NO. 112 | 1 | 1 |
| PLOT NO. 115 | 1 | 1 |
| PLOT NO. 113 | 1 | 1 |
| PLOT NO. 114 | 1 | 1 |
| PLOT NO. 230 | 1 | 1 |
| PLOT NO. 255 | 1 | 1 |
| PLOT NO. 108 | 1 | 1 |
| PLOT NO. 64 | 1 | 1 |
| PLOT NO. 117 | 1 | 1 |
| PLOT NO. 96 | 1 | 1 |
| PLOT NO. 219 | 1 | 1 |
| PLOT NO. 210 | 1 | 1 |
| PLOT NO. 95 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-07-01 | |
|---|---|---|
| Proposed completion | 2024-07-01 | |
| Revised completion | 2027-07-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q4 | 2026-01-31 | 241 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Galaxy Mining Private Limited | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AU SMALL FINANCE BANK | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| CA | Ramanand Goyal and company |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=JLZ0q6YF7xnq_O22O5PHvg
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/JLZ0q6YF7xnq_O22O5PHvg
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=JLZ0q6YF7xnq%2FO22O5PHvg%3D%3D&QuarterIdEnc=kPPHxH4RqSkp7Dvx3tlTvg%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=UZMYU%2Fm39lY%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Bankaffidavit · Sign in to download
- SitePlanPath · 2024-07-20
- LayoutPlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- Site_Plan_Doc_Sanctioned
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- SitePlanPath · 2024-07-20
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2026-01-31 · Sign in to download
- R2_UploadDoc · 2026-01-31 · Sign in to download
- R3_UploadedPath · 2026-01-31 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download