Vaishnavi Tech Park
Vaishnavi Infrastructure Pvt Ltd · Bengaluru Urban
Completion2023-05-18Revised · Proposed 2022-08-18
Registered on2019-09-13
Valid to2023-05-18
Approvals5
Complaints0
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals · 1 occupancy certificate |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details |
| Construction & progress | 3 progress details · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 65 documents · 9 source links |
Registration
Registration
| Promoter | Vaishnavi Infrastructure Pvt Ltd | |
|---|---|---|
| District | Bengaluru Urban | |
| Regulator | K-RERA | |
| Registration number | PRM/KA/RERA/1251/446/PR/190913/002853 | |
| Registered on | 2019-09-13 | |
| Valid to | 2023-05-18 | |
| Project type | Commercial | |
| Status (as filed) | APPROVED | |
| Proposed completion | 2022-08-18 | |
| Revised completion | 2023-05-18 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approved Plan | BBMP - Bruhat Bengaluru Mahanagara Palike |
| Commencement Certificate | |
| NOC issued by the Fire Force department after completion of work | |
| Occupancy Certificate | |
| Consent for operation issued by KSPCB |
Occupancy certificate
| Status | Received | |
|---|---|---|
| Date | 2022-05-07 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹28,44,58,000 | |
|---|---|---|
| Construction | ₹2,26,75,77,000 | |
| Total | ₹2,65,00,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 22,763 | |
|---|---|---|
| FAR | 2.98 | |
| Towers | 2 | |
| Maximum floors | 11 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-02-18 | |
|---|---|---|
| Proposed completion | 2022-08-18 | |
| Revised completion | 2023-05-18 |
Extensions
| Valid to | Reason |
|---|---|
| 2023-05-18 | Covid Extension |
| 2023-05-18 | Covid Extension |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Vaishnavi Infrastructure Pvt Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC | |
| Other projects in this city pack | 1 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | KATERRA INDIA PRIVATE LTD (Formerly known as KEF Infrastructure Pvt Ltd) |
| Contractor | KATERRA INDIA PRIVATE LTD (Formerly known as KEF Infrastructure Pvt Ltd) |
Sources
Sources
Source URLs & documents
- https://mahitikanaja.karnataka.gov.in/Rera/api/Rera/ProjectViewDetails
- https://rera.karnataka.gov.in/projectDetails
- https://rera.karnataka.gov.in/projectViewDetails
- https://rera.karnataka.gov.in/viewAllProjects?language=en
- Certificate · Sign in to download
- Other · Sign in to download
- Commencement Certificate
- Approved Building/Plotting Plan
- Approved Layout Plan
- Land documents and Location · Sign in to download
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Performa of Allotment Letter · Sign in to download
- Brochure of Current Project · Sign in to download
- Project Specification · Sign in to download
- Conversion Certificate under Sec 95 of the KLR Act 1961 · Sign in to download
- Fire Force Department · Sign in to download
- Airport Authority of India · Sign in to download
- BESCOM · Sign in to download
- BWSSB · Sign in to download
- KSPCB · Sign in to download
- SEIAA · Sign in to download
- BSNL · Sign in to download
- Existing Layout Plan
- Existing Section Plan and Specification
- Other · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Cash Flow Statement · Sign in to download
- Cash Flow Statement · Sign in to download
- Auditor's Report · Sign in to download
- Auditor's Report · Sign in to download
- Auditor's Report · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Declaration (Form B) · Sign in to download
- Prospectus/Brochure · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Loan raised document · Sign in to download
- Stability Certificate · Sign in to download
- Stability Certificate · Sign in to download
- NOC issued by the Fire Force department after completion of work
- Occupancy Certificate
- Consent for operation issued by KSPCB
- Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of Karnataka · Sign in to download
- on for lifts issued by the Chief of Department of Electrical inspectorate Government of Karnataka · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Architect certificate for having completed the work(in format no 5) · Sign in to download
- Chartered Accountant certificate for having completed the work(in format no 4) · Sign in to download
- Chartered Accountant certificate for having completed the work(in format no 4) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Registration certificate
- Registration certificate
- Registration Certificate
- Commencement Certificate
- NOC issued by the Fire Force department after completion of work
- Occupancy Certificate
- Consent for operation issued by KSPCB
- Extension order