Overview
VARMA KOVILAKAM
VARMA HOMES PRIVATE LIMITED · KANNANKULANKARA
Units57
Booked25 of 57
Construction progress2%
Completion2031-08-14Proposed
Registered on2026-01-12
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 7 unit types |
| Construction & progress | 3 progress details · 3 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 38 documents · 5 source links |
Registration
Registration
| Promoter | VARMA HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Ernakulam | |
| Locality | KANNANKULANKARA | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/ERN/003/2026 | |
| Registered on | 2026-01-12 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2031-08-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/102032/2025 | 2025-10-15 | 2030-10-14 | TRIPUNITHURA MUNICIPALITY ERNAKULAM |
| Development Permit | BP/102032/2025 | 2025-10-15 | 2030-10-14 | TRIPUNITHURA MUNICIPALITY ERNAKULAM |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,346 | |
|---|---|---|
| Built-up (m²) | 8,989.09 | |
| Towers | 0 | |
| Units | 57 | |
| Booked | 25 |
Unit types
| 2BHK | 9 | 2 | VARMA KOVILAKAM |
| 2BHK | 9 | 2 | VARMA KOVILAKAM |
| 2BHK | 10 | 7 | VARMA KOVILAKAM |
| 3BHK | 10 | 5 | VARMA KOVILAKAM |
| 3BHK | 9 | 3 | VARMA KOVILAKAM |
| 3BHK | 9 | 6 | VARMA KOVILAKAM |
| 4BHK | 1 | 0 | VARMA KOVILAKAM |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 2% | |
|---|---|---|
| Start | 2026-04-15 | |
| Proposed completion | 2031-08-14 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VARMA HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | South Indian Bank | |
| Other projects in this city pack | 28 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Structural solutions |
| CA | Namboodiri and co |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11218
- https://rera.kerala.gov.in/projects?district=595&page=27
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=4SbMYehqlH7seVAv41i5qZPhzpKkvLZWHTFvPVP5eCgDqPLw5zBFbeFDpRa4LN8gAdKm2q2MjdDF1TF1bkS4PJPc2%2F%2F5%2BVEufW21FLttw8EHhz2s6xq7sXT481dZKvJzqb67myMkG8tCRDXJGJcKkbhIETcFdxnhtplSWYaQglQmL1O2OlmJAg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11218&Division=1&UserID=30200&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2026-01-12
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-10-16
- Copy of Valid Building Permit · 2025-10-16
- Detailed technical specifications to be adopted in the project · 2025-12-13 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2025-10-25 · Sign in to download
- Site Plan / Site Map · 2025-10-16
- Other · 2025-12-16 · Sign in to download
- Other · 2025-12-16 · Sign in to download
- Other · 2025-12-16 · Sign in to download
- Clearance from Airport Authority of India · 2025-12-16 · Sign in to download
- Clearance from Airport Authority of India · 2025-12-16 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2025-12-15 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2025-12-15 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2025-12-15
- Consent to establish (Clearance from Pollution Control Board) · 2025-12-15 · Sign in to download
- Environment Clearance · 2025-12-15 · Sign in to download
- Initial NOC from Fire and Rescue department · 2025-12-13
- Permission from Water and sewerage department · 2025-12-15 · Sign in to download
- Charts and the project schedule · 2025-12-15 · Sign in to download
- List and details of common amenities · 2025-12-16 · Sign in to download
- Plan for Drinking water service to be executed in the proposed project · 2025-12-15
- Plan of firefighting to be executed in the proposed project · 2025-12-13
- Plan of Use of renewable energy to be executed in the proposed project · 2025-12-16