Overview
VARMA SYMPHONY
VARMA HOMES PRIVATE LIMITED · EDAPPALLY
Units26
Booked20 of 26
Construction progress46%As of 2023-12-04
Completion2030-02-28Proposed
Registered on2023-06-26
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 4 unit types |
| Construction & progress | 4 progress details · 14 quarters |
| Developer & finance | |
| Developer | 3 developer details · 4 professional firms |
| The evidence | |
| Sources | 48 documents · 6 source links |
Registration
Registration
| Promoter | VARMA HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Ernakulam | |
| Locality | EDAPPALLY | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/ERN/113/2023 | |
| Registered on | 2023-06-26 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2030-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | EYP3/199/11448/22 | 2023-04-03 | 2028-04-02 | KOCHI MUNICIPAL CORPORATION |
| Development Permit | EYP3/199/11448/22 | 2023-04-03 | 2028-04-02 | KOCHI MUNICIPAL CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,473 | |
|---|---|---|
| Built-up (m²) | 5,501.07 | |
| Towers | 0 | |
| Units | 26 | |
| Booked | 20 |
Unit types
| 2BHK | 1 | 1 | SYMPHONY |
| 3BHK | 8 | 5 | SYMPHONY |
| 3BHK | 9 | 7 | SYMPHONY |
| 3BHK | 8 | 7 | SYMPHONY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 46% | |
|---|---|---|
| As of | 2023-12-04 | |
| Start | 2023-11-01 | |
| Proposed completion | 2030-02-28 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
| 2023-2024 Q1 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VARMA HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 28 |
Professional firms
| Architect | BINUBALAKRISHNAN ARCHITECTS |
| Engineer | Structural solutions |
| CA | Namboodiri and co |
| CA | VISHNU SURESH & CO. |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=edappally%2C+Ernakulam%2C+Kerala%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.kerala.gov.in/projects/11156
- https://rera.kerala.gov.in/projects?district=595&page=27
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=vUnKtkKyhMAnVNgkdURw0CQcE0pcUx0w%2BQE3lpb1tTmPwoRhIpLlF%2Fm5M7%2FJ6208PbQj3u3YUSIjW7eTgYVlyOxSvpXSX9tD2qyXrUSFaeQTYWyxxUpdhGHxxL%2BF8%2BgRAvx%2FlGGmeSAroRAAF1uGV5gaJ1kS4d8qK7IH7I9HqJzAcawuAXz7Nw%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11156&Division=1&UserID=30200&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2023-06-26
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-04-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-04-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-05-06
- Copy of Valid Building Permit · 2023-05-06
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2023-05-06
- Detailed technical specifications to be adopted in the project · 2023-05-25 · Sign in to download
- Layout approval plan · 2023-05-25
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2023-04-12 · Sign in to download
- Site Plan / Site Map · 2023-05-06
- Other · 2023-05-06 · Sign in to download
- Other · 2023-05-06 · Sign in to download
- Other · 2023-05-06 · Sign in to download
- Clearance from Airport Authority of India · 2023-06-19 · Sign in to download
- Clearance from Airport Authority of India · 2023-06-19 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2023-05-25 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2023-06-07 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2023-05-25
- Consent to establish (Clearance from Pollution Control Board) · 2023-06-09 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2023-06-09 · Sign in to download
- Environment Clearance · 2023-05-25 · Sign in to download
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Initial NOC from Fire and Rescue department · 2023-06-07
- Permission from Water and sewerage department · 2023-05-25 · Sign in to download
- Charts and the project schedule · 2023-05-25 · Sign in to download
- List and details of common amenities · 2023-05-25 · Sign in to download
- Plan for Drinking water service to be executed in the proposed project · 2023-04-27
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of firefighting to be executed in the proposed project · 2023-06-07
- Plan of Use of renewable energy to be executed in the proposed project · 2023-06-09