DOSLKarnataka Workspace

Overview

Vasavi Nagar

Santosh Nag Pathikonda Sadashiva · Vijayanagara
Construction progress82%
Completion2029-12-31Proposed
Registered on2026-04-30
Valid to2029-12-31
Approvals7
Complaints0

Sections

Property title & search report
Approvals7 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads · 2 quarters
Technical report
Construction & progress3 progress details · 2 quarters
Developer & finance
Developer4 developer details
The evidence
Sources105 documents · 10 source links

Registration

Registration

PromoterSantosh Nag Pathikonda Sadashiva
DistrictVijayanagara
RegulatorK-RERA
Registration numberPRM/KA/RERA/1669/440/PR/300426/008608
Registered on2026-04-30
Valid to2029-12-31
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2029-12-31