Overview
VASTU VIHAR PATNA PROJECT-08
TECHNOCULTURE BUILDING CENTRE PRIVATE LIMITED · Patna
Units81
Completion2021-10-31Proposed
Registered on2019-12-16
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 8 source links |
Registration
Registration
| Promoter | TECHNOCULTURE BUILDING CENTRE PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00015-12/368/R-866/2019 | |
| Registered on | 2019-12-16 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2021-10-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹48,67,20,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 13,683.27 | |
|---|---|---|
| Built-up (m²) | 11,074.04 | |
| FAR | 0.8 | |
| Towers | 81 | |
| Units | 81 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 5 BHK | 12 | YAMUNA BUNGALOW-BIG |
| 4 BHK | 5 | YAMUNA BUNGALOW-SMALL |
| 3 BHK | 64 | JAYANTI |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2013-11-01 | |
|---|---|---|
| Proposed completion | 2021-10-31 |
Quarterly progress
| 2022-Q1 | 2022-04-16 |
| 2021-Q4 | 2022-01-17 |
| 2021-Q3 | 2021-10-11 |
| 2021-Q2 | 2021-09-04 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | TECHNOCULTURE BUILDING CENTRE PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 83 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP2311201700015-12
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP2311201700015-12
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2021-2022 · 2022-04-16
- Q3-Oct to Dec / 2021-2022 · 2022-01-17
- Q2-Jul to Sep / 2021-2022 · 2021-10-11
- Q1-Apr to Jun / 2021-2022 · 2021-09-04
- 2022-Q1 · 2022-04-16
- 2021-Q4 · 2022-01-17
- 2021-Q3 · 2021-10-11
- 2021-Q2 · 2021-09-04