DOSLChhattisgarh Workspace

Overview

VEDANTA VIHAR PHASE-1

DARSHAN DEVELOPERS · RAIPUR
Construction progress62%As of 2026-06-30
Completion2027-01-30Revised · Proposed 2025-12-31
Registered on2019-11-15
Approvals2

Sections

Property title & search report
Approvals2 approvals
Contract & costs2 cost heads · 27 quarters
Technical report
Site & area57 unit types
Construction & progress4 progress details · 27 quarters
Developer & finance
Developer3 developer details
The evidence
Sources147 documents · 5 source links

Registration

Registration

PromoterDARSHAN DEVELOPERS
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA151119001066
Registered on2019-11-15
Project typeGroup Housing
Status (as filed)New
Proposed completion2025-12-31
Revised completion2027-01-30