Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
| Building plan (BDA) | Sanctioned 4 Apr 2024 · No. PRL-42/2022-23/25 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| SEIAA | Filed with the registration |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Rent per sq ft, 3 km | ₹17.6 /mo, as listed · 5 listings with a size |
|---|
Location & risks
Construction & progress
Developer
Land · ₹3.90 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 25 Feb 2025 | |
| Building plan (BDA) | Sanctioned 4 Apr 2024 | |
| Escrow bank | Axis Bank · Vijayanagar |
Data room
81 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | 2 | Review |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| Aaradhya GardensRegistered · no quarterly update yet | SAI SAMRUDHI CONSTRUCTIONS | Apartment | 992 sqft carpet (as filed) | Dec 2028 |
| Aashirvad Siddhi PriyaFiled as completed · no completion certificate on record | SEENAPPA P | Plot | ~600–1,240 sqft (estimate: filed carpet plus 25%) | Nov 2024 |
| Aashirvad's Panchamukhi ShreyodhamaCompleted (regulator flag) | RAJESHWARI AASHIRVAD INFRA PROJECTS PRIVATE LIMITED | Plot | ~1,650 sqft (estimate: filed carpet plus 25%) | Completed |
| Aditya OrchardLapsed · completion date passed | Mangala Raghavan | Plot | ~1,200–1,800 sqft (estimate: filed carpet plus 25%) | May 2024 |
| Aprameya Brindavanam EliteCompleted (regulator flag) | Aprameya Properties Pvt Ltd | Plot | – | Completed |
| Ashwasurya Atharva RitewayCompleted (regulator flag) | RITEWAY & KUBERA PROMOTERS | Plot | ~1,200–2,400 sqft (estimate: filed carpet plus 25%) | Completed |
| Axis Banyan CountyCompleted (regulator flag) | R.Harish babu | Plot | – | Completed |
| Birla Apple SpireLapsed · completion date passed | Apple spire India LLP | Apartment | 1,667 sqft carpet (as filed) | Sep 2019 |
8 of 121 other projects in Mysore Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Vijayashree Enclave 3 in the interactive atlas
Approval or registration
Land use converted
DC Office, Bangalore · Survey 117/4, 117/9, 117/10
K-RERA filing, land schedule
Approval or registration
Land use converted
DC Office, Bangalore · Survey 117/4, 117/9, 117/10
K-RERA filing, land schedule
Approval or registration
Land use converted
DC Office, Bangalore · Survey 117/4, 117/9, 117/10
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BDA · plan PRL-42/2022-23/25
K-RERA filing, approvals
Approval or registration
Khata issued
E Khatha · Local Panchayath · Survey 117/9
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · Local Panchyath · Survey 117/10
K-RERA filing, land schedule
Approval or registration
Khata issued
E Khatha · Local panchayath · Survey 117/4
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1251/310/PR/030525/007705
K-RERA registration ·
Approval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Records searched to | 25 Feb 2025 |
|---|
| Developer's project loan | None declared |
|---|
| Filed survey numbers matched to the KGIS map | 3 of 3 | |
|---|---|---|
| Whole survey numbers on the KGIS map | 50,395 sq m | |
| Extent the filed land schedule names for these survey numbers | 6,070 sq m | |
| Plot area against the filed extent | 8.3 times | |
| Village, hobli and taluk on the KGIS map | Kumbalagodu, KENGERI - 2 hobli, BANGALORE-SOUTH taluk | |
| Mutation entry | None open on 3 of 3 filed surveys |
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 14 Nov 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Survey numbers | 117/4, 117/9, 117/10 | |
|---|---|---|
| Land extent, Sy 117/4 | 25 Guntas | |
| Land extent, Sy 117/9 | 20 Guntas | |
| Land extent, Sy 117/10 | 15 Guntas | |
| Whole survey numbers on the KGIS map | 50,395 sq m (the project holds a share) | |
| Khata | E Khatha · Local panchayath · 20 Mar 2025; E Khatha · Local Panchayath · 20 Mar 2025; E Khatha · Local Panchyath · 20 Mar 2025 |
| Survey | Owners as on the RTC, read date / relation / share | Owners on the RTC | RTC extent | Filed extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|---|
| Sy. No. 117/4 | 3 | 25 guntas | 0 | ||||
| Sy. No. 117/9 | 3 | 20 guntas | 0 | ||||
| Sy. No. 117/10 | 1 | 15 guntas | 0 |
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Mar 2026 |
| Land conversion | Converted 1 Feb 2022 · DC Office, Bangalore | |
|---|---|---|
| Survey numbers | 117/4 · 117/9 · 117/10 |
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Disputes & cases and Documents for this project, yours to read for good.
| Projects within 4 km, counted | 18 (7 with an approximate location) | |
|---|---|---|
| Plots in them | 5,879 | |
| Booked | 2,915 of 5,879 (50%) | |
| Unsold | 2,964 | |
| Booked a month, pooled | 36 plots | |
| Months to sell, pooled | 62 months |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main), at the filed pin | Clear |
|---|---|---|
| Nearest high-tension line | Nearest high-tension line: 66 kV, 120 m from the filed location | Clear |
| Nearest government-flagged flood location | 5.2 km, Kengeri Yellamma temple | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | 2.7 km to the south, Vrishabhavati, primary drain | |
|---|---|---|
| Nearest lake, tank or pond | 110 m to the west, an unnamed water body |
As the promoter reported itPossession date in the agreement

| Completion | 100% |
|---|
| Possession, agreement | 31 Mar 2026 | |
|---|---|---|
| RERA completion date | 31 Mar 2026 | |
| Work began, as filed | 1 Jun 2024 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026 (2 filed) | Clear |
|---|---|---|
| Engineer's certificate, registration | Dated 28 Feb 2025 | |
| Chartered accountant's certificate, registration | Dated 25 Feb 2025 |
| Estimated cost, at registration | ₹5.30 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹1.30 Cr | |
| Estimated cost, chartered accountant's certificate | ₹5.30 Cr, same as the filing | |
| Cost incurred | ₹1.52 Cr | |
| Cost left | ₹3.79 Cr |
| Escrow bank | Axis Bank · Vijayanagar | |
|---|---|---|
| Designated account, collected | ₹0 in Q4 2025-26 | |
| Designated account, withdrawn | ₹0 in Q4 2025-26 |
| Other phases under this promoter name | 263 | |
|---|---|---|
| With a filed extension or completion | 119 (85 completed, 34 extended) | |
| Average schedule slip | 10 months |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 23.2 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 10 CGWB wells in Bengaluru South taluk read in this class | |
| Through the year | January 2025: 2.2 m (5 wells), Pre-monsoon 2025: 1.9 m (10 wells), August 2025: 1.5 m (11 wells), depth below ground of CGWB's monitoring wells in Bengaluru South taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Kumalagodu Grama Panchayath) | |
| Nearest city water main | 5.3 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Nearest drain | 2.7 km to the south, Vrishabhavati, primary drain | |
|---|---|---|
| Ground level | 761 m above sea level, plus or minus 4 m | |
| Metro, operational | 3.4 km, Challaghatta | |
| Metro, under construction | 16.6 km, Kalena Agrahara |
| Kempegowda Airport | 56.0 | 60 | 46.0 |
| MG Road (CBD) | 23.2 | 29 | 20.6 |
| Manyata Tech Park | 33.5 | 39 | 27.0 |
| ITPL, Whitefield | 40.4 | 47 | 34.3 |
| Ecospace, Bellandur ORR | 37.0 | 40 | 26.5 |
| Electronic City Ph 1 | 33.8 | 30 | 26.0 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 1.8 km to the north-east, named STP-6 on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 790 m to the south-east, named Kumbalagodu on OpenStreetMap |