Overview
VINAY BIHAR APARTMENT
RAKESH PRASAD CHANDRABANSI · Patna
Units20
Booked2 of 20As of 2026-09-30
Construction progress57%As of 2026-09-30
Completion2029-06-29Proposed
Registered on2025-02-05
Valid to2029-06-29
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 7 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 24 documents · 13 source links |
Registration
Registration
| Promoter | RAKESH PRASAD CHANDRABANSI | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP95843-1/214/R-1805/2024 | |
| Registered on | 2025-02-05 | |
| Valid to | 2029-06-29 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-06-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | |
| Notice of Commencement in form X | |
| Environment Clearance | 2026-10-14 |
| Fire NOC | 2026-10-14 |
| Airport NOC | 2026-10-14 |
| Water Supply Permission | 2026-10-14 |
| Other approval | 2026-10-14 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹9,95,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 939.59 | |
|---|---|---|
| Built-up (m²) | 1,878.52 | |
| FAR | 1.99 | |
| Towers | 1 | |
| Units | 20 | |
| Booked | 2 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 4 | VINAY BIHAR APARTMENT |
| 3 BHK | 16 | VINAY BIHAR APARTMENT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 57% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2025-02-01 | |
| Proposed completion | 2029-06-29 |
Quarterly progress
| 2026-Q3 | 2026-10-14 | 57% | 2 |
| 2026-Q2 | 2026-07-15 | ||
| 2026-Q1 | 2026-04-24 | ||
| 2025-Q4 | 2026-01-29 | ||
| 2025-Q3 | 2025-10-17 | ||
| 2025-Q2 | 2025-07-29 | ||
| 2025-Q1 | 2025-04-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAKESH PRASAD CHANDRABANSI | |
|---|---|---|
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP11022024095843-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP11022024095843&ld=pan&pj=RERAP11022024095843-1&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP11022024095843-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-14
- Quarterly Progress Image · 2025-10-17
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-15
- Quarterly Progress Image · 2026-01-29
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-24
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-29
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-17
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-29
- Quarterly Progress Image · 2025-07-29
- Q4-Jan to Mar / 2024-2025 · 2025-04-10
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-15
- 2026-Q1 · 2026-04-24
- 2025-Q4 · 2026-01-29
- 2025-Q3 · 2025-10-17
- 2025-Q2 · 2025-07-29
- 2025-Q1 · 2025-04-10