Overview
VINAYAGA DUTTA RESIDENCY
VINAYAGA BUILDCOM · FATASIL AMBARI ROAD
Units40
Completion2026-03-31Proposed
Registered on2025-01-20
Valid to2028-03-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 11 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 19 documents · 5 source links |
Registration
Registration
| Promoter | VINAYAGA BUILDCOM | |
|---|---|---|
| District | KAMRUP METRO | |
| Locality | FATASIL AMBARI ROAD | |
| Regulator | RERA Assam | |
| Registration number | RERAA KM 180 OF 2024-2025 | |
| Registered on | 2025-01-20 | |
| Valid to | 2028-03-31 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2026-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | |||
| Building Plan | |||
| NOC/Building Permit | BUILDING PERMIT BY GMC AND PLANNING PERMIT BY GMDA | 2024-04-12 | 2026-04-12 |
| I. BUILDING PERMIT BY GMC | 2022-05-05 | ||
| II. RENEWED BUILDING PERMIT BY GMC | 2024-04-12 | ||
| III. PLANNING PERMIT BY GMDA | 2021-01-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹14,12,44,212 | |
| Total | ₹17,16,11,719 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,177.75 | |
|---|---|---|
| Units | 40 |
Unit types
| 3 | 125.14 | 5 |
| 3 | 134.1 | 5 |
| 3 | 113.24 | 5 |
| 3 | 126.15 | 5 |
| 3 | 122.17 | 5 |
| 3 | 134.16 | 1 |
| 3 | 113.16 | 1 |
| 3 | 126.16 | 1 |
| 3 | 92.11 | 4 |
| 3 | 76.11 | 4 |
| 3 | 75.11 | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-05-04 | |
|---|---|---|
| Proposed completion | 2026-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VINAYAGA BUILDCOM | |
|---|---|---|
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2130
- https://rera.assam.gov.in/view_project/searchprojectDetail/2130
- Registration Certificate
- CARPET AREA AND PARKING AREA DETAILS · 2024-07-27 · Sign in to download
- FIRE NOC · 2024-07-27
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2024-07-27 · Sign in to download
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2024-07-27 · Sign in to download
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2024-07-27 · Sign in to download
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2024-07-27 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2024-07-27
- Other · 2024-07-27 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2024-07-27
- FORM B, DULY NOTARIZED · 2024-07-27 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2024-07-27 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2024-07-27 · Sign in to download
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2024-07-27 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2024-07-27 · Sign in to download
- POWER OF ATTORNEY · 2024-07-27 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2024-07-27 · Sign in to download
- Project application order/letter · 2025-01-20 · Sign in to download
- Project application order/letter · 2024-12-23 · Sign in to download