VMS LOTUSCITY PHASE-2A

VM BUILDER AND DEVELOPERS · Kolar
Construction progress97%
Completion2027-12-31Proposed
Registered on2025-02-01
Valid to2027-12-31
Approvals9
Complaints0

Sections

Property title & search report
Approvals9 approvals
Disputes & cases0 project complaints · 1 promoter complaint
Contract & costs3 cost heads · 4 quarters
Technical report
Construction & progress3 progress details · 4 quarters
Developer & finance
Developer4 developer details
The evidence
Sources150 documents · 12 source links

Registration

Registration

PromoterVM BUILDER AND DEVELOPERS
DistrictKolar
RegulatorK-RERA
Registration numberPRM/KA/RERA/1265/339/PR/010225/007469
Registered on2025-02-01
Valid to2027-12-31
Project typePlotted Development
Status (as filed)APPROVED