Overview
VRINDAVAN CITY
SHREE LOK NATH BABA HOMES PVT LTD · Patna
Units66
Booked0 of 66As of 2026-12-31
Construction progress7%As of 2026-12-31
Completion2029-04-29Proposed
Registered on2025-04-26
Valid to2029-04-29
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 3 unit types |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 12 source links |
Registration
Registration
| Promoter | SHREE LOK NATH BABA HOMES PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP184028090425290429E00 | |
| Registered on | 2025-04-26 | |
| Valid to | 2029-04-29 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-04-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | ||
| Notice of Commencement in form X | ||
| Environment Clearance | 2025-10-08 | |
| Fire NOC | 2030-12-16 | STATE FIRE OFFICER CUM DIRECTOR BIHAR PATNA |
| Airport NOC | 2025-10-08 | |
| Water Supply Permission | 2025-10-08 | |
| Other approval | 2025-10-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹98,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,252.86 | |
|---|---|---|
| Built-up (m²) | 6,656.68 | |
| FAR | 2.95 | |
| Towers | 1 | |
| Units | 66 | |
| Booked | 0 | |
| Booked as of | 2026-12-31 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 22 | VRINDAVAN CITY |
| 3 BHK | 22 | VRINDAVAN CITY |
| 3 BHK | 22 | VRINDAVAN CITY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 7% | |
|---|---|---|
| As of | 2026-12-31 | |
| Start | 2024-07-10 | |
| Proposed completion | 2029-04-29 |
Quarterly progress
| 2026-Q4 | 2026-01-13 | 7% | 0 |
| 2026-Q3 | 2026-10-12 | ||
| 2026-Q2 | 2026-07-16 | ||
| 2026-Q1 | 2026-04-30 | ||
| 2025-Q3 | 2025-10-08 | ||
| 2024-Q2 | 2025-07-02 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHREE LOK NATH BABA HOMES PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | UCO Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP114201800263-5
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP114201800263&ld=pan&pj=RERAP114201800263-5&f=2026-2027&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP114201800263-5
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- A certificate from a Chartered accountant declaring that no advance booking amount has been taken from the customers against the current project duly signed by the promoter and countersigned by CA · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q3 (Oct - Dec) / 2026-2027 · 2026-01-13
- Quarterly Progress Image · 2025-10-08
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-12
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-16
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-30
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-08
- Q1-Apr to Jun / 2024-2025 · 2025-07-02
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q3 · 2026-10-12
- 2026-Q2 · 2026-07-16
- 2026-Q1 · 2026-04-30
- 2025-Q3 · 2025-10-08
- 2024-Q2 · 2025-07-02