Overview
VRINDAVAN RESIDENCY
BUILDMAX DEVELOPERS PRIVATE LIMITED · Patna
Booked18As of 2027-03-31
Construction progress48%As of 2027-03-31
Completion2028-06-23Proposed
Registered on2024-01-05
Valid to2028-06-23
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details |
| Construction & progress | 4 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 24 documents · 14 source links |
Registration
Registration
| Promoter | BUILDMAX DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP11052-002/134/R-1630/2024 | |
| Registered on | 2024-01-05 | |
| Valid to | 2028-06-23 | |
| Project type | Residential | |
| Status (as filed) | RERA Registered Projects | |
| Proposed completion | 2028-06-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Fire NOC | STATE FIRE OFFICER, PATNA, BIHAR |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,18,80,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 726.95 | |
|---|---|---|
| Built-up (m²) | 1,816.61 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Booked | 18 | |
| Booked as of | 2027-03-31 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 48% | |
|---|---|---|
| As of | 2027-03-31 | |
| Start | 2023-10-03 | |
| Proposed completion | 2028-06-23 |
Quarterly progress
| 2027-Q1 | 2026-04-15 | 48% | 18 |
| 2026-Q4 | 2026-01-14 | ||
| 2026-Q3 | 2026-10-15 | ||
| 2026-Q2 | 2026-07-14 | ||
| 2025-Q3 | 2025-10-15 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-10 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-07-18 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BUILDMAX DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | CANARA BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP02252022211052_002
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP02252022211052&ld=pan&pj=RERAP02252022211052_002&f=2026-2027&q=4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP02252022211052_002
- https://rera.bihar.gov.in/RCpage.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Other (if any) · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Sanction Certificate for Bank Construction Finance · Sign in to download
- Upload Sanctioned Layout Plan
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- Sanctioned Building Plan
- CA certificate · Sign in to download
- Q4 (Jan - Mar) / 2026-2027 · 2026-04-15
- Q3 (Oct - Dec) / 2026-2027 · 2026-01-14
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-15
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-14
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-15
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-10
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-18
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Other · 2026-10-07 · Sign in to download
- Other · 2026-09-25 · Sign in to download
- 2026-Q4 · 2026-01-14
- 2026-Q3 · 2026-10-15
- 2026-Q2 · 2026-07-14
- 2025-Q3 · 2025-10-15
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-10
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-18