Overview
VRRIDHAM
Balaji Land Planners LLP · Sahibzada Ajit Singh Nagar (Mohali)
Units306
Booked0 of 306As of 2026-09-30
Completion2031-02-28Proposed
Registered on2026-06-16
Valid to2031-02-28
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details · 118 unit types |
| Construction & progress | 2 progress details · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 34 documents · 18 source links |
Registration
Registration
| Promoter | Balaji Land Planners LLP | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR1389 | |
| Registered on | 2026-06-16 | |
| Valid to | 2031-02-28 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2031-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2025-05-21 | |
| CLU Certificate | ||
| Electric Substation NOC | 2026-03-30 | |
| Environment Clearance certificate/ NOC | 2026-01-12 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | 2026-04-16 | |
| Other Document (Affidavit NOC) | Legal Documents (Received) | 2026-03-17 |
| Other Document (Drainage NOC) | 2025-10-17 | |
| Other Document (Forest NOC) | 2025-11-10 | |
| Pollution Clearance from Punjab Pollution Control Board | 2026-04-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,56,05,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 21,619.401 | |
|---|---|---|
| Towers | 12 | |
| Maximum floors | 15 | |
| Units | 306 | |
| Booked | 0 | |
| Booked as of | 2026-09-30 |
Unit types
| Flat No. 1401 to 1402 and 1501 to 1502 (Fourteenth and Fifteenth Floor) | 164.915 | 2 | 0 | TOWER - 4 PENTHOUSE |
| Flat No. 1401 to 1402 and 1501 to 1502 (Fourteenth and Fifteenth Floor) | 164.915 | 2 | 0 | TOWER - 5 PENTHOUSE |
| Flat No. 101 to 104 (First Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 201 to 204 (Second Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 301 to 304 (Third Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 401 to 404 (Fourth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 501 to 504 (Fifth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 601 to 604 (Sixth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 701 to 704 (Seventh Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 801 to 804 (Eight Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 901 to 904 (Ninth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1001 to 1004 (Tenth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1101 to 1104 (Eleventh Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1201 to 1204 (Twelfth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1301 to 1304 (Thirteenth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1401 to 1404 (Fourteenth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1501 to 1504 (Fifteenth Floor) | 98.263 | 4 | 0 | TOWER - 7 3BHK |
| Flat No. 1401 to 1402 and 1501 to 1502 (Fourteenth and Fifteenth Floor) | 164.915 | 2 | 0 | TOWER - 3 PENTHOUSE |
| Flat No. 101 to 104 (First Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 201 to 204 (Second Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 301 to 304 (Third Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 401 to 404 (Fourth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 501 to 504 (Fifth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 601 to 604 (Sixth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 701 to 704 (Seventh Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 801 to 804 (Eight Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 901 to 904 (Ninth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1001 to 1004 (Tenth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1101 to 1104 (Eleventh Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1201 to 1204 (Twelfth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1301 to 1304 (Thirteenth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1401 to 1404 (Fourteenth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 1501 to 1504 (Fifteenth Floor) | 98.263 | 4 | 0 | TOWER - 8 3BHK |
| Flat No. 101 to 102 (First Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 201 to 202 (Second Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 301 to 302 (Third Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 401 to 402 (Fourth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 501 to 502 (Fifth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 601 to 602 (Sixth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 701 to 702 (Seventh Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 801 to 802 (Eight Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 901 to 902 (Ninth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1401 to 1402 (Fourteenth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 1501 to 1502 (Fifteenth Floor) | 161.504 | 2 | 0 | TOWER - 1 4BHK |
| Flat No. 101 to 102 (First Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 201 to 202 (Second Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 301 to 302 (Third Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 401 to 402 (Fourth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 501 to 502 (Fifth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 601 to 602 (Sixth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 701 to 702 (Seventh Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 801 to 802 (Eight Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 901 to 902 (Ninth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1401 to 1402 (Fourteenth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 1501 to 1502 (Fifteenth Floor) | 161.504 | 2 | 0 | TOWER - 2 4BHK |
| Flat No. 101 to 102 (First Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 201 to 202 (Second Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 301 to 302 (Third Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 401 to 402 (Fourth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 501 to 502 (Fifth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 601 to 602 (Sixth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 701 to 702 (Seventh Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 801 to 802 (Eight Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 901 to 902 (Ninth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 134.492 | 2 | 0 | TOWER - 3 3BHK |
| Flat No. 101 to 102 (First Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 201 to 202 (Second Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 301 to 302 (Third Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 401 to 402 (Fourth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 501 to 502 (Fifth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 601 to 602 (Sixth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 701 to 702 (Seventh Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 801 to 802 (Eight Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 901 to 902 (Ninth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 134.492 | 2 | 0 | TOWER - 4 3BHK |
| Flat No. 101 to 102 (First Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 201 to 202 (Second Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 301 to 302 (Third Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 401 to 402 (Fourth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 501 to 502 (Fifth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 601 to 602 (Sixth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 701 to 702 (Seventh Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 801 to 802 (Eight Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 901 to 902 (Ninth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 134.492 | 2 | 0 | TOWER - 5 3BHK |
| Flat No. 101 to 102 (First Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 201 to 202 (Second Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 301 to 302 (Third Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 401 to 402 (Fourth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 501 to 502 (Fifth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 601 to 602 (Sixth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 701 to 702 (Seventh Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 801 to 802 (Eight Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 901 to 902 (Ninth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1001 to 1002 (Tenth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1101 to 1102 (Eleventh Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1201 to 1202 (Twelfth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1301 to 1302 (Thirteenth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1401 to 1402 (Fourteenth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Flat No. 1501 to 1502 (Fifteenth Floor) | 134.435 | 2 | 0 | TOWER - 6 3BHK |
| Booth No. 1 to 12 | 32.516 | 12 | 0 | COMMERCIAL BLOCK |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-04-01 | |
|---|---|---|
| Proposed completion | 2031-02-28 |
Quarterly progress
| Quarter | Filed on | Sold | Booked |
|---|---|---|---|
| 2026-Q2 | 2026-07-15 | ||
| 2026-Q3 | 2026-10-10 | 0 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Balaji Land Planners LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| CA | SIDHARTH SAHNI AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=12692&inPromoter_ID=3620&inPromoterType=12692&inQUProject_ID=6102&inQUProject_DN=QUP2026T20266102&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12692&inPromoter_ID=3620&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-21
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2026-03-30
- Environment Clearance certificate/ NOC · 2026-01-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2026-04-16
- Other Document (Drainage NOC) · 2025-10-17
- Other Document (Forest NOC) · 2025-11-10
- Pollution Clearance from Punjab Pollution Control Board · 2026-04-30
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-21
- CLU Certificate
- Electric Substation NOC · 2026-03-30
- Environment Clearance certificate/ NOC · 2026-01-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2026-04-16
- Other Document (Affidavit NOC) · 2026-03-17
- Other Document (Drainage NOC) · 2025-10-17
- Other Document (Forest NOC) · 2025-11-10
- Pollution Clearance from Punjab Pollution Control Board · 2026-04-30
- 2026-Q2 · 2026-07-15