Overview
WAL SERENIA 92 ( VERDE 92 )
WAL DEVELOPMENTS PRIVATE LIMITED · Gurugram
Units737
Completion2029-03-31Proposed
Registered on2025-05-01
Valid to2029-07-09
Approvals19
Sections
| Property title & search report | |
|---|---|
| Approvals | 19 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 37 documents · 3 source links |
Registration
Registration
| Promoter | WAL DEVELOPMENTS PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | RC NO. GGM/938/670/2025/41 DATED 01.05.2025 IS HEREBY SUPERSEDED BY RC NO. GM/938/670/2025/41/SS(1)/1 DATED 10.08.2026 | |
| Registered on | 2025-05-01 | |
| Valid to | 2029-07-09 | |
| Status (as filed) | Registered | |
| Proposed completion | 2029-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 77 OF 2024 DATED 10/07/2024 | Town & Country Planning Department | |
| Layout Plan | 2025-01-23 | ||
| Building Plan | 2025-01-23 | ||
| I. LICENCE | 2024-07-10 | ||
| II. BUILDING PLAN | 2025-01-23 | ||
| III. DEMARCATION CUM ZONING PLAN | 2025-01-17 | ||
| IV. ENVIORNMENT CLEARANCE | 2025-01-24 | ||
| V. AIRPORTS AUTHORITY OF INDIA NOC | 2024-09-26 | ||
| VI. ARAVALI NOC | 2024-09-19 | ||
| VII. FOREST NOC | 2024-02-09 | ||
| VIII. FRESH WATER SUPPLY ASSURANCE | 2024-07-30 | ||
| IX. SEWARAGE CONNECTION ASSURANCE | 2024-07-30 | ||
| X. STORM WATER ASSURANCE | 2024-07-30 | ||
| XI. STP TREATED WATER ASSURANCE | 2024-07-30 | ||
| XII. NOC TREATED WASTE WATER FOR CONNECTION ASSURANCE | 2024-11-26 | ||
| XIII. POWER ASSURANCE | 2024-07-23 | ||
| XIV. FIRE FIGHTING SCHEME | 2025-02-06 | ||
| XV. MINING NOC | 2025-02-17 | ||
| XVI. CTE | 2025-02-17 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹91,68,79,999.9999999 | |
|---|---|---|
| Construction | ₹1,13,94,41,000 | |
| Total | ₹2,64,94,49,100 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 18,514.34 | |
|---|---|---|
| FAR | 2.4 | |
| Units | 737 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 36,692.7 | 632 |
| Apartment/Shops/Other Buildings | 2,631.11 | 105 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-04-01 | |
|---|---|---|
| Proposed completion | 2029-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | WAL DEVELOPMENTS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/3320
- https://nominatim.openstreetmap.org/search?q=sector+92%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2025-05-01
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2025-01-29 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2025-01-29 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2025-01-28 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2025-01-28
- DEMARCATION PLAN · 2025-01-28
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2025-01-28
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2025-02-11 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2025-01-29
- ZONING PLAN · 2025-01-30
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2025-01-30
- FIRE SCHEME APPROVAL LETTER · 2025-04-02
- MUTATION · 2025-04-02 · Sign in to download
- BUILDING PLAN APPROVAL LETTER FROM STP GURGAON · 2025-04-02
- POWER ASSURANCE · 2025-04-02 · Sign in to download
- FOREST NOC · 2025-04-02
- ASSURANCE- SEWERAGE CONNECTION · 2025-04-02 · Sign in to download
- BUILDING PLAN- FIRE DEPT. APPROVAL LETTER · 2025-04-02
- NOC AAI · 2025-04-02
- REVISED DEMARCATION CUM ZONING PLAN · 2025-04-02
- ENVIRONMENT CLEARANCE- WAL DEVELOPMENTS · 2025-04-02
- SIJRA · 2025-04-02 · Sign in to download
- ARRAVALI NOC · 2025-04-02
- TITLE SEARCH REPORT · 2025-04-02 · Sign in to download
- LOI · 2025-04-02 · Sign in to download
- SITE PLAN · 2025-04-02
- NOC FOR CONSTRUCTION FOR USE OF TREATED WASTE WATER · 2025-04-02
- MINING PERMISSION · 2025-04-02 · Sign in to download
- BUILDING PLAN- STP REVISED DRAWINGS APPROVAL LETTER · 2025-04-02
- BUILDING PLAN- HSVP APPROVAL LETTER · 2025-04-02
- NOC-ARAVALI · 2025-04-02
- ASSURANCE- FRESH WATER SUPPLY · 2025-04-02 · Sign in to download
- JAMABANDI · 2025-04-02 · Sign in to download
- ASSURANCE- STP TREATED WATER · 2025-04-02 · Sign in to download
- BUILDING PLAN APPROVAL LETTER · 2025-04-02
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2025-04-02
- RC No. GGM/938/670/2025/41 dated 01.05.2025 is hereby superseded by RC No. GM/938/670/2025/41/SS(1)/1 dated 10.08.2026 · 2026-08-18 · Sign in to download