Overview
WALLFORT WOOD PHASE - III
WALLFORT PROPERTIES PRIVATE LIMITED · RAIPUR
Units120
Booked22 of 120As of 2023-09-30
Construction progress100%As of 2023-09-30
Completion2023-07-19Revised · Proposed 2019-12-31
Registered on2018-06-21
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 21 quarters |
| Technical report | |
| Site & area | 3 site details · 3 unit types |
| Construction & progress | 4 progress details · 21 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 137 documents · 10 source links |
Registration
Registration
| Promoter | WALLFORT PROPERTIES PRIVATE LIMITED | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA220618000269 | |
| Registered on | 2018-06-21 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2019-12-31 | |
| Revised completion | 2023-07-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2023-02133 | CG RERA | Complaint | Disposed | 2024-03-13 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹9,38,25,000 | |
|---|---|---|
| Construction | ₹9,38,24,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹70,000 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹1,05,000 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹35,000 |
| 2020-Q1 | ₹3,15,000 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹2,000 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹7,00,000 |
| 2022-Q4 | ₹12,862.5 |
| 2023-Q1 | ₹0 |
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 120 | |
|---|---|---|
| Booked | 22 | |
| Booked as of | 2023-09-30 |
Unit types
| Type | Carpet (m²) | Units | Booked |
|---|---|---|---|
| WALLFORT WOODS1 | 273 | 107 | |
| 3BHK | 1,316.24 | 120 | 22 |
| 3BHK | 1,027.68 | 8 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-09-30 | |
| Proposed completion | 2019-12-31 | |
| Revised completion | 2023-07-19 |
Quarterly progress
| 2018-Q3 | 0% |
| 2018-Q4 | 25% |
| 2019-Q1 | 25% |
| 2019-Q2 | 25% |
| 2019-Q3 | 25% |
| 2019-Q4 | 25% |
| 2020-Q1 | 26% |
| 2020-Q2 | 26% |
| 2020-Q3 | 26% |
| 2020-Q4 | 26% |
| 2021-Q1 | 26% |
| 2021-Q2 | 26% |
| 2021-Q3 | 26% |
| 2021-Q4 | 28% |
| 2022-Q1 | 31% |
| 2022-Q2 | 83% |
| 2022-Q3 | 88% |
| 2022-Q4 | 90% |
| 2023-Q1 | 92% |
| 2023-Q2 | 94% |
| 2023-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | WALLFORT PROPERTIES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MzU3
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre
- Final order · 2024-03-13 · Sign in to download
- Interim order · 2024-02-14 · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities
- SM-EXP-2023-02133 · Sign in to download