Overview
Wave Estate, Block-D
COUNTRY COLONISERS PRIVATE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units63
Completion2018-11-30Proposed
Valid to2018-11-30
Approvals4
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 21 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 7 professional firms |
| The evidence | |
| Sources | 18 documents · 28 source links |
Registration
Registration
| Promoter | COUNTRY COLONISERS PRIVATE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0150 | |
| Valid to | 2018-11-30 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2018-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2013-09-04 |
| Application for renewal of any of the NOCs/ Licenses | 2017-09-29 |
| Electric Substation NOC | 2018-01-02 |
| Pollution Clearance from Punjab Pollution Control Board | 2018-04-11 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| CC-543-2018 | National Consumer Disputes Redressal Commission |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹25,38,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 55,255.77 | |
|---|---|---|
| Units | 63 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| 63 | 23,731.44 | 63 | BLOCK-D |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-03-18 | |
|---|---|---|
| Proposed completion | 2018-11-30 |
Quarterly progress
| 2018-Q1 | 2021-10-13 |
| 2018-Q2 | 2021-10-13 |
| 2018-Q3 | 2021-10-13 |
| 2018-Q4 | 2021-10-13 |
| 2019-Q1 | 2021-10-13 |
| 2019-Q2 | 2021-10-13 |
| 2019-Q3 | 2021-10-13 |
| 2019-Q4 | 2021-10-13 |
| 2020-Q1 | 2021-10-13 |
| 2020-Q2 | 2021-10-13 |
| 2020-Q3 | 2021-10-13 |
| 2020-Q4 | 2021-10-13 |
| 2021-Q1 | 2021-10-13 |
| 2021-Q2 | 2021-10-13 |
| 2021-Q3 | 2021-10-13 |
| 2022-Q4 | 2023-03-16 |
| 2021-Q4 | 2023-03-16 |
| 2022-Q2 | 2023-03-16 |
| 2022-Q1 | 2023-03-16 |
| 2022-Q3 | 2023-03-16 |
| 2023-Q1 | 2023-05-16 |
Extensions
| Valid to |
|---|
| 2023-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | COUNTRY COLONISERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES Bank Limited | |
| Other projects in this city pack | 20 |
Professional firms
| Agent | CASTLE LANDCON PRIVATE LTD |
| Agent | CHADHA REALTORS P LTD |
| Agent | MONGA REALTORS PVT LTD |
| Engineer | MEHRO CONSULTANTS |
| Architect | STUDIO DRA INTERNATIONAL DESIGNERS PVT LTD |
| Contractor | ABHILASHA ENTERPRISES |
| Contractor | MEP LEC PROJECTS INDIA PVT LTD |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10391&inPromoter_ID=1017&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2013-09-04
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2018-04-12
- Application for renewal of any of the NOCs/ Licenses · 2017-09-29
- Borewell Registration certificate from Central Ground Water Authority · 2016-04-19
- Building Permit Issue from Municipal Authority · 2018-04-12 · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Completion/ Phase Completion certificate from Municipal/ Competent Authority · 2018-09-12 · Sign in to download
- Electric Substation NOC · 2018-01-02
- Pollution Clearance from Punjab Pollution Control Board · 2018-04-11
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2013-09-04
- Application for renewal of any of the NOCs/ Licenses · 2017-09-29
- Electric Substation NOC · 2018-01-02
- Pollution Clearance from Punjab Pollution Control Board · 2018-04-11
- 2018-Q1 · 2021-10-13
- 2018-Q2 · 2021-10-13
- 2018-Q3 · 2021-10-13
- 2018-Q4 · 2021-10-13
- 2019-Q1 · 2021-10-13
- 2019-Q2 · 2021-10-13
- 2019-Q3 · 2021-10-13
- 2019-Q4 · 2021-10-13
- 2020-Q1 · 2021-10-13
- 2020-Q2 · 2021-10-13
- 2020-Q3 · 2021-10-13
- 2020-Q4 · 2021-10-13
- 2021-Q1 · 2021-10-13
- 2021-Q2 · 2021-10-13
- 2021-Q3 · 2021-10-13
- 2022-Q4 · 2023-03-16
- 2021-Q4 · 2023-03-16
- 2022-Q2 · 2023-03-16
- 2022-Q1 · 2023-03-16
- 2022-Q3 · 2023-03-16
- 2023-Q1 · 2023-05-16