Overview
WestFace
SAMVAAD NIRMAN DEVELOPERS · Ahmedabad
Units109
Booked74 of 109
Construction progress87.25%As of 2020-01
Completion2019-12-31Proposed
Registered on2017-09-08
Valid to2019-12-31
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 63 unit types |
| Construction & progress | 4 progress details · 7 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 45 documents · 32 source links |
Registration
Registration
| Promoter | SAMVAAD NIRMAN DEVELOPERS | |
|---|---|---|
| District | Ahmedabad | |
| Regulator | GujRERA | |
| Registration number | PR/GJ/AHMEDABAD/AHMADABAD CITY/AUDA/CAA00110/A1C/280918 | |
| Registered on | 2017-09-08 | |
| Valid to | 2019-12-31 | |
| Project type | Commercial | |
| Status (as filed) | Public completed project list | |
| Proposed completion | 2019-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| documents.projectdoc.allNOCsfromAuthoritiesUId | Ahmedabad Municipal Corporation |
| Commencement Certificate | Ahmedabad Municipal Corporation |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹24,99,82,360 | |
|---|---|---|
| Construction | ₹24,22,60,000 | |
| Total | ₹49,22,42,360 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,461 | |
|---|---|---|
| Towers | 1 | |
| Units | 109 | |
| Booked | 74 |
Unit types
| Shop | 102 | 1 | 0 | Building 1 |
| Shop | 29.15 | 1 | 0 | Building 1 |
| Shop | 84.23 | 2 | 2 | Building 1 |
| Office | 83.54 | 3 | 3 | Building 1 |
| Office | 81.86 | 3 | 3 | Building 1 |
| Office | 36.67 | 6 | 5 | Building 1 |
| Office | 35.59 | 3 | 3 | Building 1 |
| Office | 97.95 | 2 | 0 | Building 1 |
| Office | 37.33 | 3 | 3 | Building 1 |
| Office | 37.34 | 3 | 3 | Building 1 |
| Office | 38.36 | 3 | 2 | Building 1 |
| Office | 38.58 | 3 | 2 | Building 1 |
| Office | 46.89 | 3 | 2 | Building 1 |
| Office | 35.25 | 3 | 3 | Building 1 |
| Office | 35.18 | 3 | 2 | Building 1 |
| Office | 36.54 | 3 | 2 | Building 1 |
| Office | 35.24 | 3 | 1 | Building 1 |
| Office | 34.15 | 3 | 3 | Building 1 |
| Office | 33.13 | 3 | 3 | Building 1 |
| Office | 107.62 | 1 | 1 | Building 1 |
| Office | 36.24 | 3 | 1 | Building 1 |
| Office | 70.62 | 3 | 2 | Building 1 |
| Shop | 96.74 | 1 | 0 | Building 1 |
| Shop | 97.45 | 1 | 0 | Building 1 |
| Shop | 97.18 | 1 | 1 | Building 1 |
| Shop | 96.86 | 1 | 0 | Building 1 |
| Shop | 97.36 | 1 | 1 | Building 1 |
| Shop | 97.21 | 1 | 0 | Building 1 |
| Shop | 95.32 | 1 | 0 | Building 1 |
| Shop | 60.46 | 1 | 0 | Building 1 |
| Shop | 111.34 | 1 | 0 | Building 1 |
| Shop | 130.48 | 1 | 0 | Building 1 |
| Shop | 28.9 | 1 | 0 | Building 1 |
| Shop | 37.35 | 1 | 0 | Building 1 |
| Shop | 39.28 | 1 | 0 | Building 1 |
| Shop | 38.92 | 1 | 0 | Building 1 |
| Shop | 174.75 | 1 | 0 | Building 1 |
| Shop | 86.02 | 1 | 1 | Building 1 |
| Shop | 85.87 | 1 | 1 | Building 1 |
| Shop | 86.24 | 1 | 0 | Building 1 |
| Shop | 86.04 | 1 | 0 | Building 1 |
| Shop | 375.12 | 1 | 0 | Building 1 |
| Shop | 146.21 | 1 | 0 | Building 1 |
| Office | 34.22 | 3 | 2 | Building 1 |
| Office | 84.37 | 1 | 1 | Building 1 |
| Office | 82.38 | 1 | 1 | Building 1 |
| Office | 39.46 | 1 | 1 | Building 1 |
| Office | 36.42 | 2 | 1 | Building 1 |
| Office | 36.29 | 2 | 2 | Building 1 |
| Office | 37.41 | 1 | 1 | Building 1 |
| Office | 35.35 | 1 | 1 | Building 1 |
| Office | 36.06 | 1 | 1 | Building 1 |
| Office | 35.92 | 1 | 1 | Building 1 |
| Office | 120.25 | 1 | 1 | Building 1 |
| Office | 37.91 | 3 | 3 | Building 1 |
| Office | 39.31 | 2 | 2 | Building 1 |
| Office | 37.63 | 1 | 1 | Building 1 |
| Office | 71.88 | 1 | 1 | Building 1 |
| Office | 48.28 | 1 | 1 | Building 1 |
| Office | 141.89 | 1 | 1 | Building 1 |
| Office | 55.53 | 1 | 1 | Building 1 |
| Office | 46.07 | 1 | 1 | Building 1 |
| Office | 70.33 | 1 | 0 | Building 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 87.25% | |
|---|---|---|
| As of | 2020-01 | |
| Start | 2016-08-01 | |
| Proposed completion | 2019-12-31 |
Quarterly progress
| 2018-Q2 | 2018-08-07 | 66.77% |
| 2018-Q3 | 2018-09-10 | 71.8% |
| 2018-Q4 | 2018-10-05 | 76.57% |
| 2019-Q1 | 2019-01-04 | 72.64% |
| 2019-Q2 | 2019-04-01 | 87.25% |
| 2019-Q4 | 2019-07-05 | |
| 2020-Q1 | 87.25% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAMVAAD NIRMAN DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://gujrera.gujarat.gov.in/dashboard/cost-category-wise-completed-list/GUJARAT/total
- https://gujrera.gujarat.gov.in/dashboard/get-all-block-chart-details-by-id/574
- https://gujrera.gujarat.gov.in/dashboard/get-all-view-unit-details-by-id/574
- https://gujrera.gujarat.gov.in/dashboard/get-district-wise-projectlist-alt/0/0/all/Ahmedabad/all
- https://gujrera.gujarat.gov.in/dashboard/get-district-wise-projectlist/0/0/all/Ahmedabad/all
- https://gujrera.gujarat.gov.in/dashboard/get-district-wise-projectlist/0/0/all/all/all
- https://gujrera.gujarat.gov.in/form_five/get-formfive-records-till-date/574
- https://gujrera.gujarat.gov.in/formone/public/getfrom-one-byformone-id/18197
- https://gujrera.gujarat.gov.in/formone/public/getpublicform-one-form-two-id/574
- https://gujrera.gujarat.gov.in/formone/public/project/noc/getnoc-by-proj-proid-type/574/18197
- https://gujrera.gujarat.gov.in/formthree/public/get-fromthree-a-details-byid/241839
- https://gujrera.gujarat.gov.in/formthree/public/get-fromthree-b-details-byid/241839
- https://gujrera.gujarat.gov.in/formthree/public/get-fromthree-c-details-byid/241839
- https://gujrera.gujarat.gov.in/formthree/public/get-inv-details-for-view
- https://gujrera.gujarat.gov.in/formtwo/public/getform-two-by-id/20888
- https://gujrera.gujarat.gov.in/maplocation/public/getProjectLocations/574
- https://gujrera.gujarat.gov.in/project_reg/project-app/getproject-blocklist/574
- https://gujrera.gujarat.gov.in/project_reg/public/alldatabyprojectid/574
- https://gujrera.gujarat.gov.in/project_reg/public/getProjectProgressReports-ByPrjRegId/574
- https://gujrera.gujarat.gov.in/project_reg/public/getprev-project-list/574
- https://gujrera.gujarat.gov.in/project_reg/public/getproject-details/574
- https://gujrera.gujarat.gov.in/project_reg/public/getproject-doc/574
- https://gujrera.gujarat.gov.in/project_reg/public/project-app/getproject-banks/574
- https://gujrera.gujarat.gov.in/project_reg/public/projectAllApplications/574
- https://gujrera.gujarat.gov.in/quarter/get-by-project-id/574
- https://gujrera.gujarat.gov.in/quarter/get-project-progress/574
- https://gujrera.gujarat.gov.in/quarter/getformpdf-by-id/574
- https://gujrera.gujarat.gov.in/quarter/public/get-qtr-form-details/574
- https://gujrera.gujarat.gov.in/quarter/public/getprojectqtrs/574
- https://nominatim.openstreetmap.org/search?q=thaltej%2C+Ahmedabad%2C+Gujarat%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- applications.certificate · 2017-07-28 · Sign in to download
- previous_projects.gujrera.projectImageUId · Sign in to download
- documents.projectdoc.brochureOfCurrentProjectDocUId · Sign in to download
- form_documents.form_one_pdf_uid · 2019-07-05
- documents.projectdoc.commencementCertDocUId
- detail.projectDetail.declarationFormbNewDocUId · Sign in to download
- form_documents.form_two_pdf_uid · 2017-07-28
- form_documents.form_one_pdf_uid · 2018-05-30
- form_documents.form_one_pdf_uid · 2018-08-07
- form_documents.form_two_pdf_uid · 2018-08-07
- form_documents.form_one_pdf_uid · 2018-09-10
- form_documents.form_two_pdf_uid · 2018-09-10
- form_documents.form_one_pdf_uid · 2018-10-05
- form_documents.form_two_pdf_uid · 2018-10-05
- form_documents.form_one_pdf_uid · 2019-01-04
- form_documents.form_two_pdf_uid · 2019-01-04
- form_documents.form_one_pdf_uid · 2019-04-01
- form_documents.form_two_pdf_uid · 2019-04-01
- form_two.formTwoPdfUId
- documents.findoc.auditedBalSheetDoc1UId · Sign in to download
- documents.findoc.auditedBalSheetDoc2_UId · Sign in to download
- documents.findoc.auditedBalSheetDoc3UId · Sign in to download
- documents.findoc.auditedProfitLossSheetDoc1UId · Sign in to download
- documents.findoc.auditedProfitLossSheetDoc2UId · Sign in to download
- documents.findoc.auditedProfitLossSheetDoc3UId · Sign in to download
- documents.findoc.cashFlowStmtFileDoc1UId · Sign in to download
- documents.findoc.cashFlowStmtFileDoc2UId · Sign in to download
- documents.findoc.cashFlowStmtFileDoc3UId · Sign in to download
- documents.projectdoc.auditorsDoc1UId · Sign in to download
- documents.projectdoc.auditorsDoc2UId · Sign in to download
- documents.projectdoc.auditorsDoc3UId · Sign in to download
- documents.projectdoc.projectSpecificDocUId · Sign in to download
- documents.projectdoc.directorReportDoc1UId · Sign in to download
- documents.projectdoc.directorReportDoc2UId · Sign in to download
- documents.projectdoc.directorReportDoc3UId · Sign in to download
- documents.projectdoc.approvedBuildingPlanPlottingPlanUId
- documents.projectdoc.approveLayoutPlanDocUId
- documents.projectdoc.areaDevelopmentDocUId · Sign in to download
- Document
- documents.projectdoc.declarationFormbDocUId · Sign in to download
- annual.pdfUid
- annual.pdfUid · 2019-10-16
- completion.qt_addidavit_docuid · Sign in to download
- completion.five_doc_uid · Sign in to download
- completion.qt_form_four_a_docuid · Sign in to download
- documents.projectdoc.allNOCsfromAuthoritiesUId
- Commencement Certificate