Overview
WESTFORT INEOS
WESTFORT REALTORS PRIVATE LIMITED · Guruvayoor Road
Units99
Booked21 of 99
Construction progress15%
Completion2029-06-20Proposed
Registered on2024-06-26
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 3 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 53 documents · 5 source links |
Registration
Registration
| Promoter | WESTFORT REALTORS PRIVATE LIMITED | |
|---|---|---|
| District | Thrissur | |
| Locality | Guruvayoor Road | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/TSR/124/2024 | |
| Registered on | 2024-06-26 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2029-06-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Building Permit | BP/13787/2025-Revision-01 | 2024-02-21 | 2029-02-20 | GURUVAYUR MUNICIPALITY THRISSUR |
| Building Permit | BA-289/2019/20 | 2024-02-21 | 2029-02-20 | Guruvayur Municipality |
| Development Permit | BA-289/2019/20 | 2024-02-21 | 2029-02-20 | MUNICIPALITY |
| Development Permit | BP/13787/2025-Revision-01 | 2024-02-21 | 2029-02-20 | GURUVAYUR MUNICIPALITY, THRISSUR |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,327.69 | |
|---|---|---|
| Built-up (m²) | 12,910.03 | |
| Towers | 0 | |
| Units | 99 | |
| Booked | 21 |
Unit types
| 1BHK | 25 | 6 | WESTFORT INEOS |
| 2BHK | 25 | 10 | WESTFORT INEOS |
| 2BHK | 25 | 4 | WESTFORT INEOS |
| 3BHK | 12 | 1 | WESTFORT INEOS |
| 3BHK | 12 | 0 | WESTFORT INEOS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 15% | |
|---|---|---|
| Start | 2024-02-27 | |
| Proposed completion | 2029-06-20 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | WESTFORT REALTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | THE FEDERAL BANK LTD | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | ARYARCH ARCHITECTS |
| Engineer | ASSOCIATED STRUCTURAL CONSULTANTS |
| CA | VIPIN K K AND CO |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11392
- https://rera.kerala.gov.in/projects?district=594&page=12
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=Om%2FdDe2WzURyTck2d8nKVuExlUQYR5xb5HXCS%2BCRFCehPProlzAB5zA8LOb4Q8%2FBVIZxJisJjS3iJNO66CLlJClieOfJ%2FyUQF4ETIC5K%2FBObzaFL7l01oRa4iFPAIP0x8Emnj1xOT57i7CvWPL2dkVAKSfmKtVwgT%2B19dQwQgHrZlRsFUHQFfg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11392&Division=1&UserID=33197&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2024-06-26
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-03-30
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-04-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-04-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-04-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-04-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-04-29
- Copy of Valid Building Permit · 2024-03-05
- Copy of Valid Building Permit · 2026-04-29
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2024-03-09
- Detailed technical specifications to be adopted in the project · 2023-11-08 · Sign in to download
- Layout approval plan · 2024-04-18
- Layout approval plan · 2026-04-29
- Layout approval plan · 2026-04-29
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2024-03-30 · Sign in to download
- Site Plan / Site Map · 2024-03-30
- Site Plan / Site Map · 2026-04-29
- Other · 2023-11-08 · Sign in to download
- Architect's Certificate in Form No 2 · 2024-06-10 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2024-03-16 · Sign in to download
- Initial NOC from Fire and Rescue department · 2023-11-08
- Initial NOC from Fire and Rescue department · 2026-04-29
- Permission from Water and sewerage department · 2023-11-09 · Sign in to download
- Others · 2024-06-22 · Sign in to download
- Others · 2024-06-24 · Sign in to download
- Others · 2024-06-24 · Sign in to download
- Others · 2024-06-24 · Sign in to download
- Others · 2026-07-10 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Others · 2026-07-31 · Sign in to download
- Charts and the project schedule · 2024-06-10 · Sign in to download
- List and details of common amenities · 2023-11-09 · Sign in to download
- Plan for Drinking water service to be executed in the proposed project · 2023-11-09
- Plan for Drinking water service to be executed in the proposed project · 2023-11-09
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of firefighting to be executed in the proposed project · 2023-11-10
- Plan of Use of renewable energy to be executed in the proposed project · 2023-11-08
- Brochure / prospectus issued in regard to this project · 2024-06-10 · Sign in to download
- Brochure / prospectus issued in regard to this project · 2026-05-15 · Sign in to download
- Final Fire NOC · 2024-06-10