No survey sketch is listed on this phase's MahaRERA filing
Not verified yet: Title opinion; Records searched to; Charges on the land; Landowner share of sales; How the land reached this project; Title report; Boundary schedule; Encumbrance certificate; Sketch, sanction and mutation; Survey plots · cadastral; Land record; The RTC of each filed survey; Share of sales revenue; Joint development agreement.
Approvals
Is it approved for its use?
RERA extensionsNone on the filingFiling read 31 Oct 2026
Permits
Approval letters
Building plan approval
2 filed · latest filed 2 Sep 2021
RERA
MahaRERA
RERA extensions
None on the filing
RERA completion date
30 Sep 2027
Disputes & cases
Are there court cases or buyer complaints on this project?
Review1 to review
Builder: Classic Promoters and Builders Private Limited
Court cases on the project's land
0 cases
The filing names no land owners, so there is no name to search.
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
None listed.
Court cases against the builder and landowners
0 cases
Filed on
Case no.
Filed at
Location
Filed by
Against
What it's about
Status
Search pending.
Buyer complaints filed with MahaRERA on this project
0 cases
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
Filed on
Case no.
Filed at
Location
Filed by
What it's about
Status
None listed.
Buyer complaints on other projects by this builder✓Confirmed
2 cases
Other status 2
Contract & costs
What does a buyer commit to?
We haven't verified this for this project yet.
Sign in first, then it is one click.
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Agreement for sale.
Not verified yet: Groundwater; Water supply, as filed; Metro, operational; Power lines, flood-prone areas, drains; Planning and hazards; Site vs nearest drain; Drains and lakes; Specification and Form 5; Water at a glance; Within 3 km; Measured from the site; Road distance from the site; Six city anchors · OSRM, no traffic; Distance from the site; DOSL nuisance layer.
Construction & progress
How is it being built, and when will it be ready?
CompletionFirst return due
Progress
Completion, architect
Registered: its first quarterly return is still to come
Work left
By component
Registered: its first quarterly return is still to come
Quarterly return
Registered: its first quarterly return is still to come
Dates
Dates
Developer
Can the developer deliver?
Receivable, sold units₹95.49 CrBalance due on 38 sold and booked units, as of 31 Oct 2026
Cost left₹69.48 CrEstimated ₹242.63 Cr less incurred ₹173.15 Cr
Sold37 / 98MahaRERA register
Sold in the latest quarterFirst return due
Funding
Estimated cost
Loan & collateral
Can it be financed?
Value, 3,186 sq ft unit₹4.04 CrCarpet × median registered agreement price
Max loan₹3.03 Cr75% LTV ceiling
Borrower margin₹1.01 CrThe value less the most a bank may lend
Developer's project loan₹48.00 Cr securedBorrowed funds filed with MahaRERA
Value & LTV
3,186 sq ft unit, carpet
Data room
Documents filed for this project
Documents filed6On MahaRERA
Available467% of filed
MahaRERA only2
Approvals with a validity dateNone read
Quarterly certificates
Filed 2024-12-27Available
Filed 2024-12-27Available
Filed 2024-12-27Available
Filed 2024-12-27Available
Source: MahaRERA project page and the documents filed there, as read by us. 167 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
Registration certificates
Registration number
P52100030319
Registered
15 Aug 2021
Not verified yet: Building plan, Land conversion, Validity, Power NOC, Fire NOC, Environmental clearance, Airport height NOC, Pollution board (CFE), Conversion order.
✓Confirmed: the record names this project, its land or its promoter company?Likely: matched by the builder's nameHigh: a court stay or a pending case on the filed landMedium: open, or the record does not sayLow: decided or closed
17
₹13,355
3,122 sq ft · 290.04 sq m
1
1
0
–
3,186 sq ft · 295.99 sq m
31
3
28
₹12,695
3,334 sq ft · 309.74 sq m
7
3
4
₹16,417
3,519 sq ft · 326.92 sq m
21
15
6
₹13,524
3,645–3,650 sq ft · 338.6–339.1 sq m
4
1
3
–
By building
Building
Units filed
Sold
Median ₹/sq ft carpet
Building 1 1st floor to 25 floor
77
37
₹13,389
Building 2 26th floor to 32nd floor
21
1
–
Floor plans, brochure
No floor plans on file
Unsold stock
Unsold units
Carpet area
Unsold units
Carpet area, total
2,904 sq ft · 269.79 sq m
1
2,904 sq ft
2,949 sq ft · 273.97 sq m
1
2,949 sq ft
2,993–3,008 sq ft · 278.1–279.4 sq m
17
50,896 sq ft
3,186 sq ft · 295.99 sq m
28
89,208 sq ft
3,334 sq ft · 309.74 sq m
4
13,336 sq ft
3,519 sq ft · 326.92 sq m
6
21,114 sq ft
3,645–3,650 sq ft · 338.6–339.1 sq m
3
10,935 sq ft
All unsold
60
1,91,342 sq ft
Not verified yet: Recent price, super built-up; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; Pune, Maharashtra, past year; Pune, Maharashtra since 2022; This project vs Pune, Maharashtra; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Nearest 12 with filed prices; This project vs the nearest with filed prices; Median rent, 3 km; Rents and yields; Months to sell unsold stock; MahaRERA inventory.
Filed dates
RERA completion date
30 Sep 2027
Registered
15 Aug 2021
Completion date first filed
30 Mar 2025
Certificates
Engineer, architect and fire certificates
Architect's certificate, Form 1
1 filed · latest filed 27 Dec 2024
Chartered accountant's certificate, Form 3
3 filed · latest filed 27 Dec 2024
Not verified yet: Possession, agreement; Structure; Structural safety certificate; Schedule end; What the promoter specified · not an inspection; Specification sheet, page 1; Specification sheet · brands "or equivalent"; Structural engineer, quarterly; Design consultants (Form 6); Fire safety; Environmental clearance.
Land · ₹36.18 Cr 14.9%Development · ₹206.45 Cr 85.1%
Cost left vs buyer dues
Form 4
Estimated cost, at registration
₹242.63 Cr
Sales
Sold vs unsold
Sold 38.1%Unsold 61.9%
Sold per quarter
Registered: its first quarterly return is still to come
MahaRERA inventory
Units filed
98
Sold
37 · 38%
Unsold
60
Compliance
Escrow
Registered: its first quarterly return is still to come
Escrow and filings
Escrow balance
₹15,161.92 (INR)
Filed withdrawal amount
₹51,27,79,645.55 (INR)
Track record
Average schedule slip
DOSL builder track
Other phases under this promoter name
13
With a filed extension or completion
12 (0 completed, 12 extended)
Average schedule slip
37 months
Not verified yet: Cost incurred; Cost left; Collected from buyers; Receivable, sold units; Land cost revision; Escrow bank; Designated account, collected; Designated account, withdrawn; Unregistered agreements, over 10% paid.
Calculation
3,186 sq ft unit
Carpet area
3,186 sq ft
Median registered agreement price
₹12,695 /sq ft
Estimated value
₹4.04 Cr
LTV ceiling
75%
Max loan
₹3.03 Cr
Borrower margin
₹1.01 Cr
Conditions
Collateral checks
Developer's project loan
₹48.00 Cr secured
Building plan
Approval filed with MahaRERA · latest 2 Sep 2021
Stage
Certified progress
Registered: its first quarterly return is still to come
Not verified yet: Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of; Escrow bank.