Units2,632
Completion2017-12-31Proposed
Registered on2017-08-14
Valid to2017-12-31
Approvals3
Complaints4As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 4 project complaints · 272 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 32 documents · 8 source links |
Registration
Registration
| Promoter | GREATER NOIDA INDUSTRIAL DEVELOPMENT AUTHORITY | |
|---|---|---|
| District | Gautam Buddha Nagar | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ10104 | |
| Registered on | 2017-08-14 | |
| Valid to | 2017-12-31 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2017-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 2017-08-01 | 2022-07-31 | Greater Noida Authority | |
| Original permit | PLANNING/2009/D.S.-122/1408 | 2017-08-01 | 2018-07-17 | Greater Noida Authority |
| Revalidated permit | PLANNING/2009/D.S.-122/1408 | 2017-08-01 | 2020-03-20 | Greater Noida Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 4 | |
|---|---|---|
| Promoter | 272 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹3,42,55,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,47,558 | |
|---|---|---|
| Units | 2,632 |
Unit types
| Type | Units |
|---|---|
| 150 to 200 sqm | 1,156 |
| 100 to 150 sqm | 1,476 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2009-01-14 | |
|---|---|---|
| Proposed completion | 2017-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GREATER NOIDA INDUSTRIAL DEVELOPMENT AUTHORITY | |
|---|---|---|
| Type | Other | |
| Escrow bank | BANK OF BARODA | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=7eES3jk8mlA=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=H94thmkB53PHPdv4RZd90A==&PaURJEMAN4=ZL9MNERkNdYu/65BbBGlmQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/WebService1.asmx/loadPlot_new
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GAUTAM%20BUDDHA%20NAGAR
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=7eES3jk8mlA=
- Details of Encumbrances · 2018-07-28 · Sign in to download
- Commencement Certificate · 2018-07-28
- Proforma of Application Form · 2018-07-28 · Sign in to download
- Proforma of Allotment Letter · 2018-07-28 · Sign in to download
- Proforma of Conveyance Deed · 2018-07-28 · Sign in to download
- Water Supply Plan · 2018-07-28
- Electricity Supply Plan · 2018-07-28
- Development Work Plan · 2018-07-28
- Affidavit (Form-B) · 2018-07-28 · Sign in to download
- CA CERTIFICATE · 2018-07-31 · Sign in to download
- ENGINEERS CERTIFICATE · 2018-07-31 · Sign in to download
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Electricity Supply Plan · 2017-08-12
- Proforma of Application Form · 2017-08-12 · Sign in to download
- Proforma of Application Form · 2017-08-12 · Sign in to download
- Proforma of Allotment Letter · 2017-08-12 · Sign in to download
- Proforma of Conveyance Deed · 2017-08-12 · Sign in to download
- Waste Disposal Plan · 2017-08-12
- Water Supply Plan · 2017-08-12
- Commencement Certificate · 2017-08-12
- Authentic copy of Approval of Project · 2017-08-12
- Sanctioned Layout Plan (Of Entire Project) · 2017-08-12
- Details of Encumbrances · 2017-08-12 · Sign in to download
- Registry Document In Case of Own Land · 2017-08-12 · Sign in to download
- Registry Document In Case of Own Land · 2017-08-12 · Sign in to download
- Registry Document In Case of Own Land · 2017-08-12 · Sign in to download