Overview
YADURAJ OXYGEN ACRES
ARYAN LANDMARK DEVELOPERS LLP · DHANKIYA ROAD
Units530
Booked243 of 530As of 2023-12-31
Completion2024-06-30Revised · Proposed 2022-06-29
Registered on2022-07-20
Valid to2024-06-30
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 166 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 182 documents · 6 source links |
Registration
Registration
| Promoter | ARYAN LANDMARK DEVELOPERS LLP | |
|---|---|---|
| District | Jaipur | |
| Locality | DHANKIYA ROAD | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/2070 | |
| Registered on | 2022-07-20 | |
| Valid to | 2024-06-30 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-06-29 | |
| Revised completion | 2024-06-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹36,00,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹61,00,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2023-Q4 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,00,000 | |
|---|---|---|
| Built-up (m²) | 55,236.23 | |
| Towers | 530 | |
| Units | 530 | |
| Booked | 243 | |
| Booked as of | 2023-12-31 |
Unit types
| 233 | 1 | 0 |
| 232 | 1 | 0 |
| 231 | 1 | 0 |
| 230 | 1 | 0 |
| 229 | 1 | 0 |
| 325 | 1 | 0 |
| 234 | 1 | 0 |
| 228 | 1 | 0 |
| 227 | 1 | 0 |
| 226 | 1 | 0 |
| 225 | 1 | 0 |
| 224 | 1 | 0 |
| 223 | 1 | 0 |
| 222 | 1 | 0 |
| 221 | 1 | 0 |
| 239 TO 251, 254 TO 266 | 26 | 0 |
| 220 | 1 | 0 |
| 219 | 1 | 0 |
| 175 | 1 | 0 |
| 218 | 1 | 0 |
| 217 | 1 | 0 |
| 216 | 1 | 0 |
| 176 | 1 | 0 |
| 215 | 1 | 0 |
| 214 | 1 | 0 |
| 41 TO 46, 49 TO 70, 74 TO 86, 101 TO 113, 193 TO 210, 276 TO 282, 287 TO 293 | 86 | 0 |
| 177 | 1 | 0 |
| 236 | 1 | 0 |
| 48 | 1 | 0 |
| 178 | 1 | 0 |
| 273 | 1 | 0 |
| 88 TO 93, 95 TO 99, 140 TO 149, | 21 | 0 |
| 296 TO 308 | 13 | 0 |
| 2 TO 6, 9 TO 13, 15 TO 18 | 14 | 0 |
| 72 | 1 | 0 |
| 235 | 1 | 0 |
| 283, 286 | 2 | 0 |
| 190 | 1 | 0 |
| 272 | 1 | 0 |
| 40 | 1 | 0 |
| 237 | 1 | 0 |
| 252, 253 | 2 | 0 |
| 212 | 1 | 0 |
| 189 | 1 | 0 |
| 71 | 1 | 0 |
| 324 | 1 | 0 |
| 37, 38, 39, 117, 125, 127, 128, 130, 135, 136, 137, 152 TO 161, 164 TO 173, 191, 311 TO 323, 326, 327, 330 TO 335 | 53 | 0 |
| 188 | 1 | 0 |
| 271 | 1 | 0 |
| 284, 285 | 2 | 0 |
| 115 | 1 | 0 |
| 187 | 1 | 0 |
| 73, 114 | 2 | 0 |
| 180 TO 183 | 4 | 0 |
| 309 | 1 | 0 |
| 134 | 1 | 0 |
| 213 | 1 | 0 |
| 270 | 1 | 0 |
| 30 | 1 | 0 |
| 186 | 1 | 0 |
| 29 | 1 | 0 |
| 7, 8 | 2 | 0 |
| 32 | 1 | 0 |
| 31 | 1 | 0 |
| 238, 267 | 2 | 0 |
| 33 | 1 | 0 |
| 34 | 1 | 0 |
| 28 | 1 | 0 |
| 138, 192, 310 | 3 | 0 |
| 269 | 1 | 0 |
| 35 | 1 | 0 |
| 185 | 1 | 0 |
| 27 | 1 | 0 |
| 274 | 1 | 0 |
| 268 | 1 | 0 |
| 1, 14, 19 | 3 | 0 |
| 179 | 1 | 0 |
| 87, 94, 100, 139, 275, 294 | 6 | 0 |
| 295 | 1 | 0 |
| 116, 126, 129 | 3 | 0 |
| 162, 174 | 2 | 0 |
| 150 | 1 | 0 |
| 328 | 1 | 0 |
| 21 | 1 | 0 |
| 26 | 1 | 0 |
| 47 | 1 | 0 |
| 184 | 1 | 0 |
| 151, 163 | 2 | 0 |
| 25 | 1 | 0 |
| 24 | 1 | 0 |
| 22 | 1 | 0 |
| 20 | 1 | 0 |
| 23 | 1 | 0 |
| 133 | 1 | 0 |
| 36 | 1 | 0 |
| 118 | 1 | 0 |
| 119 | 1 | 0 |
| 329 | 1 | 0 |
| 120 | 1 | 0 |
| 123, 124, 131, 132 | 4 | 0 |
| 121 | 1 | 0 |
| 122 | 1 | 0 |
| S-1 TO S-67 | 67 | 0 |
| C-1 | 1 | 0 |
| C-2 | 1 | 0 |
| L-20 | 1 | 0 |
| L-28 | 1 | 0 |
| L-29 | 1 | 0 |
| L-3 TO L-11 | 9 | 0 |
| L-21 | 1 | 0 |
| L-23 | 1 | 0 |
| L-30 | 1 | 0 |
| L-17 | 1 | 0 |
| L-31 | 1 | 0 |
| L-19 | 1 | 0 |
| L-34 | 1 | 0 |
| L-24 | 1 | 0 |
| L-12 | 1 | 0 |
| L-32 | 1 | 0 |
| L-18 | 1 | 0 |
| L-25 | 1 | 0 |
| L-42 | 1 | 0 |
| L-13 , L-16 | 2 | 0 |
| L-14, L-15 | 2 | 0 |
| L-37 TO L-41 | 5 | 0 |
| L-33 | 1 | 0 |
| L-35 | 1 | 0 |
| L-44 | 1 | 0 |
| L-02 | 1 | 0 |
| L-22 | 1 | 0 |
| L-26 | 1 | 0 |
| L-36 | 1 | 0 |
| L-1 | 1 | 0 |
| L-27 | 1 | 0 |
| L-43 | 1 | 0 |
| E-26 | 1 | 0 |
| E-25 | 1 | 0 |
| E-22 TO E-24 | 3 | 0 |
| E-40 TO E-44 | 5 | 0 |
| E-27 | 1 | 0 |
| E-28 | 1 | 0 |
| E-29 | 1 | 0 |
| E-30 | 1 | 0 |
| E-21 | 1 | 0 |
| E-31 | 1 | 0 |
| E-32 | 1 | 0 |
| E-33 | 1 | 0 |
| E-34 | 1 | 0 |
| E-35 | 1 | 0 |
| E-39 | 1 | 0 |
| E-38 | 1 | 0 |
| E-36 | 1 | 0 |
| E-37 | 1 | 0 |
| E-1 TO E-20 | 20 | 0 |
| C-2 TO C-6, C-17 TO C-30 (JDA SECTOR COMMERCIAL) | 19 | 0 |
| C-1 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-31 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-32 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-33 (JDA SECTOR COMMERCILA) | 1 | 0 |
| C-34 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-35 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-36 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-37 (JDA SECTOR COMMERCIAL) | 1 | 0 |
| C-7 TO C-16 (KHATEDAR SECTOR COMMERCIAL) | 10 | 0 |
| C- 38 (KHATEDAR SECTOR COMMERCIAL) | 1 | 0 |
| 211 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-06-29 | |
|---|---|---|
| Proposed completion | 2022-06-29 | |
| Revised completion | 2024-06-30 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2023-Q4 | 2024-01-31 | 243 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ARYAN LANDMARK DEVELOPERS LLP | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD. | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=NyREwMRUuFvseui_ouYAtQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/NyREwMRUuFvseui_ouYAtQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=NyREwMRUuFvseui%2FouYAtQ%3D%3D&QuarterIdEnc=lJHGa8ZaZ%2F%2B%2BMHueLod9FA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=kcKN8fCQq8A%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2022-06-29
- Copy Of Approved Site Plan
- Water supply Permission
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- SitePlanPath · 2022-06-29
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2023-10-06 · Sign in to download
- R2_UploadDoc · 2023-10-06 · Sign in to download
- R3_UploadedPath · 2024-01-31 · Sign in to download