Overview
Yaduraj SAMSARA
ARYAN LANDMARK DEVELOPERS LLP · Jaipur
Units70
Booked32 of 70As of 2024-12-31
Completion2027-05-10Revised · Proposed 2024-01-10
Registered on2024-01-29
Valid to2027-05-10
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 51 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 73 documents · 6 source links |
Registration
Registration
| Promoter | ARYAN LANDMARK DEVELOPERS LLP | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/2943 | |
| Registered on | 2024-01-29 | |
| Valid to | 2027-05-10 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2024-01-10 | |
| Revised completion | 2027-05-10 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹11,11,72,697 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹14,65,89,437 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q4 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 32,292 | |
|---|---|---|
| Built-up (m²) | 18,463.12 | |
| Towers | 70 | |
| Units | 70 | |
| Booked | 32 | |
| Booked as of | 2024-12-31 |
Unit types
| 1 | 1 | 0 |
| 2 | 1 | 0 |
| 3 | 1 | 0 |
| 4 | 1 | 0 |
| 5 | 1 | 0 |
| 6 | 1 | 0 |
| 7 | 1 | 0 |
| 8 | 1 | 0 |
| 9 | 1 | 0 |
| 10 | 1 | 0 |
| 11 | 1 | 0 |
| 12 | 1 | 0 |
| 13 | 1 | 0 |
| 14 | 1 | 0 |
| 15 | 1 | 0 |
| 16 | 1 | 0 |
| 17 | 1 | 0 |
| 18 | 1 | 0 |
| 19 | 1 | 0 |
| 20,25,27 | 3 | 0 |
| 24 | 1 | 0 |
| 28 | 1 | 0 |
| 29 | 1 | 0 |
| 30 | 1 | 0 |
| 31 | 1 | 0 |
| 32 | 1 | 0 |
| 33 | 1 | 0 |
| 34 | 1 | 0 |
| 35 | 1 | 0 |
| 36 | 1 | 0 |
| 21,22,26 | 3 | 0 |
| 23 | 1 | 0 |
| C-1 | 1 | 0 |
| C-2 | 1 | 0 |
| Retail Shop RC-1 | 1 | 0 |
| E-1,E-2,E-3,E-6,E-7,E-8 | 6 | 0 |
| E-4 | 1 | 0 |
| E-5 | 1 | 0 |
| E-9,E-10,E-11 | 3 | 0 |
| E-12 | 1 | 0 |
| E-13 | 1 | 0 |
| E-14 | 1 | 0 |
| E-15 | 1 | 0 |
| L-1,L-2 | 2 | 0 |
| L-3,L-4,L-5 | 3 | 0 |
| L-6,L-7,L-8 | 3 | 0 |
| L-9 | 1 | 0 |
| L-10,L-11,L-12 | 3 | 0 |
| L-13,L-14 | 2 | 0 |
| L-15 | 1 | 0 |
| L-16 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-01-10 | |
|---|---|---|
| Proposed completion | 2024-01-10 | |
| Revised completion | 2027-05-10 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q4 | 2025-01-31 | 32 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ARYAN LANDMARK DEVELOPERS LLP | |
|---|---|---|
| Type | Company | |
| Escrow bank | KOTAK MAHINDRA BANK | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=7DGA_KpDvPc-bzOtjP6M1g
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/7DGA_KpDvPc-bzOtjP6M1g
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=7DGA%2FKpDvPc%2BbzOtjP6M1g%3D%3D&QuarterIdEnc=fJ0qjqph7wECoDCiZzFW1g%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=CwekcRLYJVw%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2024-01-11
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2024-01-01
- LayoutPlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-01
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-10
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- SitePlanPath · 2024-01-11
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-12-31 · Sign in to download
- R2_UploadDoc · 2025-01-31 · Sign in to download
- R3_UploadedPath · 2025-01-30 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download