Overview
YAMINI ENCLAVE
YAMINI CONSTRUCTIONS · Visakhapatnam
Units20
Completion2023-09-29Proposed
Registered on2021-03-25
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 20 unit types |
| Construction & progress | 2 progress details · 21 quarters |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | YAMINI CONSTRUCTIONS | |
|---|---|---|
| District | Visakhapatnam | |
| Regulator | AP RERA | |
| Registration number | P03240101483 | |
| Registered on | 2021-03-25 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-09-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date |
|---|---|---|
| Building / layout plan | 1086/0795/B/Z6/CDA/2020 | 2020-09-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,12,05,000 | |
|---|---|---|
| Construction | ₹3,05,42,717.73 | |
| Total | ₹4,17,47,717.73 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 624.12 | |
|---|---|---|
| Built-up (m²) | 1,993.19 | |
| Towers | 1 | |
| Units | 20 |
Unit types
| 2BHK | 56.99 | 1 | BLOCK 1 | FIRST |
| 2BHK | 61.37 | 1 | BLOCK 1 | FIRST |
| 2BHK | 59.67 | 1 | BLOCK 1 | FIRST |
| 2BHK | 63.85 | 1 | BLOCK 1 | FIRST |
| 2BHK | 56.99 | 1 | BLOCK 1 | FOURTH |
| 2BHK | 61.37 | 1 | BLOCK 1 | FOURTH |
| 2BHK | 59.67 | 1 | BLOCK 1 | FOURTH |
| 2BHK | 63.85 | 1 | BLOCK 1 | FOURTH |
| 2BHK | 56.99 | 1 | BLOCK 1 | GROUND |
| 2BHK | 61.37 | 1 | BLOCK 1 | GROUND |
| 2BHK | 59.67 | 1 | BLOCK 1 | GROUND |
| 2BHK | 63.85 | 1 | BLOCK 1 | GROUND |
| 2BHK | 56.99 | 1 | BLOCK 1 | SECOND |
| 2BHK | 61.37 | 1 | BLOCK 1 | SECOND |
| 2BHK | 59.67 | 1 | BLOCK 1 | SECOND |
| 2BHK | 63.85 | 1 | BLOCK 1 | SECOND |
| 2BHK | 56.99 | 1 | BLOCK 1 | THIRD |
| 2BHK | 61.37 | 1 | BLOCK 1 | THIRD |
| 2BHK | 59.67 | 1 | BLOCK 1 | THIRD |
| 2BHK | 63.85 | 1 | BLOCK 1 | THIRD |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-09-29 | |
|---|---|---|
| Proposed completion | 2023-09-29 |
Quarterly progress
| 2021-Q2 | 2021-08-31 |
| 2021-Q3 | 2021-10-22 |
| 2021-Q4 | 2022-01-21 |
| 2022-Q1 | 2022-04-20 |
| 2022-Q2 | 2022-07-20 |
| 2022-Q3 | 2022-10-21 |
| 2022-Q4 | 2023-01-20 |
| 2023-Q1 | 2023-04-20 |
| 2023-Q2 | 2023-07-22 |
| 2023-Q3 | 2023-10-20 |
| 2023-Q4 | 2024-01-12 |
| 2024-Q1 | 2024-04-22 |
| 2024-Q2 | 2024-07-16 |
| 2024-Q3 | 2024-10-25 |
| 2024-Q4 | 2025-01-27 |
| 2025-Q1 | 2025-04-28 |
| 2025-Q2 | 2025-07-21 |
| 2025-Q3 | 2025-10-30 |
| 2025-Q4 | 2026-01-29 |
| 2026-Q1 | 2026-04-21 |
| 2026-Q2 | 2026-07-21 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | YAMINI CONSTRUCTIONS | |
|---|---|---|
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFT6gPp1F3TRqELpdAsWSNzHStbAq9kXjBuFTYVawaxulhwBW1GIHHrMlaKdp/UVCq2EzuoP/ibbioZTBlyjGGbqvMQo/a6L6b4hNy2RGy0xk
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE