ZARA AAVAAS-3
PERFECT BUIDWELL PVT LTD · Gurugram
Units316
Completion2024-07-01Proposed
Registered on2021-07-27
Valid to2026-12-31
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 40 documents · 3 source links |
Registration
Registration
| Promoter | PERFECT BUIDWELL PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/464/196/2021/32 DATED 27.07.2021 | |
| Registered on | 2021-07-27 | |
| Valid to | 2026-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-07-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 72 of 2019 | Town & Country Planning Department | |
| Layout Plan | 2020-11-11 | ||
| Building Plan | 2020-11-11 | ||
| I. ISSUANCE OF ARAVALI CLEARENCE | 2019-08-06 | ||
| II. NO OBJECTION CERTIFICATE FOR HEIGHT CLEARENCE | 2019-08-26 | ||
| III. ASSURANCE CERTIFICATE OF DHBVNL | 2019-09-11 | ||
| IV. ASSURANCE FOR SEWERAGE CONNECTION | 2019-09-04 | ||
| V. ASSURANCE OF DRINKING WATER | 2019-09-02 | ||
| VI. ASSURANCE FOR SUPPLY OF 80 KLD STP TREATED WATER | 2019-09-04 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹38,89,43,000 | |
|---|---|---|
| Construction | ₹28,00,00,000 | |
| Total | ₹78,09,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,231.9 | |
|---|---|---|
| FAR | 2.25 | |
| Units | 316 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 54.012 | 224 |
| Apartment/Shops/Other Buildings | 59.77 | 92 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-04-30 | |
|---|---|---|
| Proposed completion | 2024-07-01 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PERFECT BUIDWELL PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1473
- https://nominatim.openstreetmap.org/search?q=sector+104%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2021-07-27
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-12-25
- DEMARCATION PLAN · 2020-12-25
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2020-12-25 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-12-25 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2020-12-25 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-12-25 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-12-25 · Sign in to download
- ZONING PLAN · 2020-12-25
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-01-21
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-01-21
- COMMERCIAL 4,5 AND 6 FLOOR PLAN AND AREA CALCULATION · 2021-01-21
- ELEVATION D TOWER 24 · 2021-01-21 · Sign in to download
- ELEVATION TOWER 25,26 · 2021-01-21 · Sign in to download
- ELEVATION A TOWER 25,26 · 2021-01-21 · Sign in to download
- ELEVATION C TOWER 25,26 · 2021-01-21 · Sign in to download
- GREEN PLAN AND AREA CALCULATION · 2021-01-21
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-01-21
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-01-21
- COMMERCIAL 4,5 AND 6 TERRECE PLAN AND AREA CALCULATION · 2021-01-21
- ELEVATION B TOWER 24 · 2021-01-21 · Sign in to download
- ELEVATION A TOWER 24 · 2021-01-21 · Sign in to download
- SECTION AA TOWER 25,26 · 2021-01-21 · Sign in to download
- SERVICE PLAN · 2021-01-21
- TOWER 24 GROUND AND TYPICAL FLOOR PLAN 1ST TO 9TH · 2021-01-21
- SITE FLOOR PLAN PARKING AREA CALCULATION · 2021-01-21
- SITE PLAN · 2021-01-21
- STILT FLOOR AND PARKING AREA · 2021-01-21 · Sign in to download
- TOWER 24 TERRECE PLAN MUMTY LEVEL PLAN AND MACHIENE ROOM · 2021-01-21
- TOWER 24 10,11,12TH FLOOR PLAN AND AREA CALCULATION · 2021-01-21
- SECTION AA TOWER 24 · 2021-01-21 · Sign in to download
- TOWER 25,26 TERRECE PLAN MUMTY LEVEL PLAN AND MACHIENE ROOM · 2021-01-21
- ELEVATION B TOWER 25,26 · 2021-01-21 · Sign in to download
- BALANCESHEET 2016-2017 · 2021-01-22 · Sign in to download
- BALACESHEET 2017-2018 · 2021-01-23 · Sign in to download
- CASH FLOW STATEMENT FOR ZARA AAVAAS · 2021-01-22 · Sign in to download
- CASH FLOW STATEMENT FOR ZARA AAVAAS2 · 2021-01-22 · Sign in to download
- BALANCESHEET 2018-2019 · 2021-01-23 · Sign in to download
- Extension No. 08 of 2025 dated 21.02.2025 · 2025-02-24 · Sign in to download
- EXTENSION IN PROJECT CONTINUATION WITH RC NO. RC/REP/HARERA/GGM/32 of 2021/7(3)/87/2025/29 DATED 16.10.2025 · 2026-04-15 · Sign in to download