Overview
ZIRAKPUR BAZAAR
Mittaso Projects Private Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units145
Completion2022-12-12Proposed
Valid to2022-12-11
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 145 unit types |
| Construction & progress | 2 progress details · 7 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 37 documents · 17 source links |
Registration
Registration
| Promoter | Mittaso Projects Private Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0218 | |
| Valid to | 2022-12-11 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2022-12-12 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2022-03-21 | |
| License as Promoter from competent Authority | Permissions (Received) | 2021-12-03 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2022-10-11 | |
| NOC from Fire Department/ Chief Fire Officer | 2023-11-04 | |
| Other Document (DRAINAGE NOC) | 2024-02-02 | |
| Other Document (Forest NOC) | 2023-12-12 | |
| Pollution Clearance from Punjab Pollution Control Board | 2023-11-25 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹6,95,16,064 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,832.8 | |
|---|---|---|
| Towers | 2 | |
| Maximum floors | 3 | |
| Units | 145 |
Unit types
| SHOP - 1 (GF) | 20.16 | 1 | BLOCK A |
| SHOP - 2 (GF) | 20.717 | 1 | BLOCK A |
| SHOP - 5 (GF) | 13.099 | 1 | BLOCK A |
| SHOP - 3 (GF) | 20.717 | 1 | BLOCK A |
| SHOP - 4 (GF) | 20.067 | 1 | BLOCK A |
| SHOP - 6 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 7 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 8 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 9 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 10 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 11 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 12 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 13 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 14 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 15 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 16 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 17 (GF) | 17.651 | 1 | BLOCK A |
| SHOP - 18 (GF) | 12.727 | 1 | BLOCK A |
| SHOP - 19 (GF) | 14.307 | 1 | BLOCK A |
| SHOP - 20 (GF) | 17.651 | 1 | BLOCK A |
| SHOP - 21 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 22 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 23 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 24 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 25 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 26 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 27 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 28 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 29 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 30 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 31 (GF) | 18.394 | 1 | BLOCK A |
| SHOP - 32 (GF) | 13.192 | 1 | BLOCK A |
| SHOP - 101 A (FF) | 9.104 | 1 | BLOCK A |
| SHOP - 102 A (FF) | 9.661 | 1 | BLOCK A |
| SHOP - 103 A (FF) | 9.104 | 1 | BLOCK A |
| SHOP - 101 (FF) | 9.104 | 1 | BLOCK A |
| SHOP - 102 (FF) | 9.661 | 1 | BLOCK A |
| SHOP - 103 (FF) | 9.104 | 1 | BLOCK A |
| SHOP - 104 (FF) | 8.825 | 1 | BLOCK A |
| SHOP - 105 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 106 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 107 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 108 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 109 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 110 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 111 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 112 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 113 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 114 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 115 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 116 (FF) | 14.307 | 1 | BLOCK A |
| SHOP - 117 (FF) | 8.454 | 1 | BLOCK A |
| SHOP - 118 (FF) | 154 | 1 | BLOCK A |
| SHOP - 119 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 120 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 121 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 122 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 123 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 124 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 125 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 126 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 127 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 128 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 129 (FF) | 14.957 | 1 | BLOCK A |
| SHOP - 130 (FF) | 8.825 | 1 | BLOCK A |
| SHOP - 201 A (SF) | 9.104 | 1 | BLOCK A |
| SHOP - 202 A (SF) | 9.661 | 1 | BLOCK A |
| SHOP - 203 A (SF) | 9.104 | 1 | BLOCK A |
| SHOP - 201 (SF) | 9.104 | 1 | BLOCK A |
| SHOP - 202 (SF) | 9.661 | 1 | BLOCK A |
| SHOP - 203 (SF) | 9.104 | 1 | BLOCK A |
| SHOP - 204 (SF) | 8.825 | 1 | BLOCK A |
| SHOP - 205 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 206 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 207 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 208 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 209 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 210 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 211 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 212 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 213 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 214 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 215 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 216 (SF) | 14.307 | 1 | BLOCK A |
| SHOP - 217 (SF) | 8.454 | 1 | BLOCK A |
| SHOP - 218 (SF) | 14.307 | 1 | BLOCK A |
| SHOP - 219 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 220 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 221 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 222 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 223 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 224 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 225 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 226 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 227 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 228 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 229 (SF) | 14.957 | 1 | BLOCK A |
| SHOP - 230 (SF) | 8.825 | 1 | BLOCK A |
| SHOP - 301 A (TF) | 9.104 | 1 | BLOCK A |
| SHOP - 302 A (TF) | 9.661 | 1 | BLOCK A |
| SHOP - 303 A (TF) | 9.104 | 1 | BLOCK A |
| SHOP - 301 (TF) | 9.104 | 1 | BLOCK A |
| SHOP - 302 (TF) | 9.661 | 1 | BLOCK A |
| SHOP - 303 (TF) | 9.104 | 1 | BLOCK A |
| SHOP - 304 (TF) | 8.825 | 1 | BLOCK A |
| SHOP - 305 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 306 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 307 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 308 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 309 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 310 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 311 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 312 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 313 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 314 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 315 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 316 (TF) | 14.307 | 1 | BLOCK A |
| SHOP - 317 (TF) | 8.454 | 1 | BLOCK A |
| SHOP - 318 (TF) | 14.307 | 1 | BLOCK A |
| SHOP - 319 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 320 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 321 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 322 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 323 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 324 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 325 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 326 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 327 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 328 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 329 (TF) | 14.957 | 1 | BLOCK A |
| SHOP - 330 (TF) | 8.825 | 1 | BLOCK A |
| SHOP - 33 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 34 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 35 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 36 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 37 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 38 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 39 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 40 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 41 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 42 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 43 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 44 (GF) | 16.443 | 1 | BLOCK B |
| SHOP - 45 (GF) | 27.87 | 1 | BLOCK B |
| SHOP - 46 (GF) | 109 | 1 | BLOCK B |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-01-01 | |
|---|---|---|
| Proposed completion | 2022-12-12 |
Quarterly progress
| 2024-Q2 | 2024-07-30 |
| 2024-Q3 | 2025-01-16 |
| 2025-Q1 | 2025-04-14 |
| 2025-Q2 | 2025-07-18 |
| 2025-Q3 | 2026-01-15 |
| 2025-Q4 | 2026-01-16 |
| 2024-Q4 | 2025-01-16 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Mittaso Projects Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11417&inPromoter_ID=2285&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Building Permit Issue from Municipal Authority · 2021-02-12 · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2022-03-21
- License as Promoter from competent Authority · 2021-12-03
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-10-11
- NOC from Fire Department/ Chief Fire Officer · 2023-11-04
- Occupancy Certificate from Municipal/ Competent Authority · 2022-12-12 · Sign in to download
- Other Document (CA CERTIFICATE) · 2024-02-06 · Sign in to download
- Other Document (CA REPORT) · 2023-10-26 · Sign in to download
- Other Document (Cash Flow 3 Years) · 2023-12-29 · Sign in to download
- Other Document (DRAINAGE NOC) · 2024-02-02
- Other Document (Forest NOC) · 2023-12-12
- Other Document (Name Change, Road Access) · 2023-12-22 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2023-11-25
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2022-03-21
- License as Promoter from competent Authority · 2021-12-03
- NOC from Fire Department/ Chief Fire Officer · 2022-10-11
- NOC from Fire Department/ Chief Fire Officer · 2023-11-04
- Other Document (DRAINAGE NOC) · 2024-02-02
- Other Document (Forest NOC) · 2023-12-12
- Pollution Clearance from Punjab Pollution Control Board · 2023-11-25
- 2024-Q2 · 2024-07-30
- 2024-Q3 · 2025-01-16
- 2025-Q1 · 2025-04-14
- 2025-Q2 · 2025-07-18
- 2025-Q3 · 2026-01-15
- 2025-Q4 · 2026-01-16
- 2024-Q4 · 2025-01-16